Hold a Weekly 15-Minute Call With the Lead
The tile setter and the painter both show up Monday, for the same room. A delivery arrives when nobody can sign for it. A fifteen-minute call each week to walk through the next two weeks takes fifteen minutes. The question is how likely a schedule collision is each week for the call to pay.
The steps
- Price the call: minutes × the value of your time, per week.
- Price a schedule collision: a wasted crew day and a day of delay.
- Break-even weekly chance = call cost ÷ collision cost.
- Send the plan too (text the crew tomorrow’s plan the evening before).
A worked example
Example (illustrative arithmetic, not predictions)
The call takes 15 minutes at $60 an hour: $15 a week. A schedule collision costs $300. Every figure is a made-up round number.
| Weekly chance of a schedule collision | Expected cost avoided (chance × $300) | Avoided − $15 |
|---|---|---|
| 2.5% | $7.50 | −$7.50 |
| 5% | $15 | $0 (break-even) |
| 10% | $30 | +$15 |
| 15% | $45 | +$30 |
The call pays at a 5% weekly chance of a schedule collision: $15 ÷ $300. Over a flip with several trades, it is plausible.
Pick a fixed time, go through who is on site, what is delivered, what inspections are due and what could collide, and send a two-line recap by text. Put scope and price changes in writing.
Making it routine
- Pick a fixed time each week.
- Go through crew, deliveries, inspections and collisions.
- Send a two-line recap by text.
- Put scope and price changes in writing.