Salvage at Demo: The Sale Price That Pays for the Hours

By DeskTech HQ · · 1 min read

Demolition produces a pile of things that still work: kitchen cabinets, appliances, doors. Throwing them in a dumpster costs dump fees. Taking them out whole and selling them costs hours. The question is what they have to sell for to make the hours worth it.

The steps

  1. Value the extra hours to remove, list and hand over the items.
  2. Subtract the dump fees you avoid.
  3. Break-even sale price = hours cost − dump fees avoided.
  4. Add any carrying days if removal slows the schedule (debris and dumpsters).

A worked example

Example (illustrative arithmetic, not market values)

Salvage takes 6 extra hours at $40, $240. It avoids $150 of dump fees. Every figure is a made-up round number.

Sale price of the salvage Sale + dump fees avoided − hours ($240)
$50 −$40
$90 $0 (break-even)
$600 +$510

The salvage has to sell for about $90: $240 − $150. A set of decent kitchen cabinets and a working range easily clear that. A single scuffed door does not.

The risk is time. Items that do not sell sit in the garage and the property, and demolition that waits on salvage delays the rehab. Set a deadline, give or donate what is left, and count any delay in carrying days (the cleanout question).

Making it routine

  1. Walk the house for salvageable items before demolition.
  2. Check for asbestos, lead and refrigerants first.
  3. Compute the break-even sale price.
  4. Set a pickup deadline and dispose of the rest.

Run your own numbers

Use the free holding cost calculator below to see what each day of delay costs on a project.

Quick answers

What is the break-even sale price?

The cost of your hours minus the dump fees you avoid.

What can be salvaged?

Cabinets, appliances, fixtures and lumber in decent condition.

Are there hazards?

Yes. Asbestos, lead and refrigerants have rules. Check before you remove anything.

Does the time delay the rehab?

It can. Count carrying days if removal slows the schedule.

Do the numbers in this guide apply to my project?

No. The costs and prices are made up for the example. They are not market values.