Ask for a Written Start and Finish Date for Each Trade
The painter finishes on Thursday and the floor refinisher is booked to start the same day in the same rooms. Nobody saw it coming. A one-page schedule with each trade’s start and finish dates takes twelve minutes to ask for and check. The question is how likely a trade-overlap delay is for the schedule to pay.
The steps
- Price the schedule: minutes × the value of your time.
- Price a trade-overlap delay: a day or more of delay.
- Break-even chance = schedule cost ÷ delay cost.
- Set the remedy too (late-finish penalties in contractor contracts).
A worked example
Example (illustrative arithmetic, not predictions)
The schedule takes 12 minutes at $60 an hour: $12. A trade-overlap delay costs $400. Every figure is a made-up round number.
| Chance of a trade-overlap delay | Expected cost avoided (chance × $400) | Avoided − $12 |
|---|---|---|
| 1.5% | $6 | −$6 |
| 3% | $12 | $0 (break-even) |
| 6% | $24 | +$12 |
| 10% | $40 | +$28 |
The schedule pays at a 3% chance of a trade-overlap delay: $12 ÷ $400. On a rehab with many trades, it is plausible.
Ask for the start and finish date of each trade and check for overlaps and gaps, share the schedule with the crew and update it weekly. Put remedies for delay in the written contract.
Making it routine
- Ask for the start and finish date of each trade.
- Check for overlaps and gaps.
- Share the schedule with the crew and update it weekly.
- Put remedies for delay in the written contract.
Run your own numbers
Use the free holding cost calculator below to see what a day of delay costs on your own flip.