Late-Finish Charges in Contractor Contracts: The Daily Rate
A contractor promises twelve weeks and takes fourteen. Each extra day costs the owner interest, taxes and insurance. A late-finish charge is meant to shift part of that cost back. The question is what daily rate makes sense.
The steps
- Compute your holding cost per day (holding costs).
- Decide what share of a day’s delay is clearly caused by the contractor’s schedule.
- Set a daily rate near a reasonable estimate of your loss, not far above it.
- Compare the recovery for the delay you fear with your actual cost of that delay.
- Consider a matching bonus for early finish, and what each does to the bid.
A worked example
Example (illustrative arithmetic, not standards)
Your holding cost is $150 a day. The contractor finishes 12 days late, so the delay costs you 12 × $150 = $1,800. Compare three daily charges. Every figure is a made-up round number.
| Daily charge | Recovered over 12 days | Your cost of delay | Unrecovered |
|---|---|---|---|
| $50 | $600 | $1,800 | $1,200 |
| $100 | $1,200 | $1,800 | $600 |
| $150 | $1,800 | $1,800 | $0 |
A daily charge equal to your holding cost fully repays the delay and is the easiest to defend as a real estimate of loss. A lower rate repays only part. A rate above your real cost may be challenged as a penalty rather than agreed damages. The contractor may also build the charge into the price, or refuse the clause, so ask for bids with and without it (comparing contractor bids).
Two cautions. Delays caused by you, such as late decisions or a stalled draw, or by weather, usually need to be carved out, or the clause can create disputes (weather delays). And a clause does not replace schedule management: a contractor who is late is often a contractor who is underfunded or overbooked (contractor payment schedule and change orders).
Making it routine
- Know your daily holding cost before you negotiate.
- Ask for bids with and without a late-finish clause.
- Carve out delays that are not the contractor’s.
- Have an attorney draft and review the clause.