Ask the Contractor to Confirm Weather Delay Days in Writing

By DeskTech HQ · · 1 min read

The job runs two weeks late, and the contractor says eight of those days were rain. You counted three. A written note for each weather day, sent at the time, takes three minutes. The question is how likely a contested delay is for the note to pay.

The steps

  1. Price the note: minutes × the value of your time.
  2. Price a contested delay: time and goodwill arguing over how many days were lost.
  3. Break-even chance = note cost ÷ dispute cost.
  4. Plan for it (padding exterior work for weather delays).

A worked example

Example (illustrative arithmetic, not predictions)

The note takes 3 minutes at $60 an hour: $3. A contested delay costs $300. Every figure is a made-up round number.

Chance of a contested delay Expected cost avoided (chance × $300) Avoided − $3
0.5% $1.50 −$1.50
1% $3 $0 (break-even)
3% $9 +$6
5% $15 +$12

The note pays at a 1% chance of a contested delay: $3 ÷ $300. On exterior work, it is easily exceeded.

Ask for a note naming each weather day and the work stopped, send it at the time and check it against the contract’s delay terms.

Making it routine

  1. Ask for a note naming each weather day.
  2. Name the work it stopped.
  3. Send it at the time.
  4. Check it against the contract’s delay terms.

Run your own numbers

Use the free holding cost calculator below to see what each lost day costs on your own flip.

Quick answers

What do you ask for?

A text or email naming each weather delay day and the work it stopped.

How do I price it?

The minutes to ask and file the reply times the value of your time.

What does a contested delay cost?

Time and goodwill arguing over how many days were really lost.

What is the break-even chance?

The step's cost divided by that cost.

Do the numbers in this guide apply to my flip?

No. The costs and odds are made up for the example. They are not predictions.

Keep reading

Flip project management

Ask for a Photo of Each Delivered Material Pallet

Learn how to price asking the contractor for a photo of each delivered material pallet and find the short-shipment chance at which two minutes pays.

· 1 min read

This guide is general education, not legal, tax, or financial advice. Talk with a licensed professional about your situation.