Ask the Contractor to Confirm Weather Delay Days in Writing
The job runs two weeks late, and the contractor says eight of those days were rain. You counted three. A written note for each weather day, sent at the time, takes three minutes. The question is how likely a contested delay is for the note to pay.
The steps
- Price the note: minutes × the value of your time.
- Price a contested delay: time and goodwill arguing over how many days were lost.
- Break-even chance = note cost ÷ dispute cost.
- Plan for it (padding exterior work for weather delays).
A worked example
Example (illustrative arithmetic, not predictions)
The note takes 3 minutes at $60 an hour: $3. A contested delay costs $300. Every figure is a made-up round number.
| Chance of a contested delay | Expected cost avoided (chance × $300) | Avoided − $3 |
|---|---|---|
| 0.5% | $1.50 | −$1.50 |
| 1% | $3 | $0 (break-even) |
| 3% | $9 | +$6 |
| 5% | $15 | +$12 |
The note pays at a 1% chance of a contested delay: $3 ÷ $300. On exterior work, it is easily exceeded.
Ask for a note naming each weather day and the work stopped, send it at the time and check it against the contract’s delay terms.
Making it routine
- Ask for a note naming each weather day.
- Name the work it stopped.
- Send it at the time.
- Check it against the contract’s delay terms.