Weather Delays: Padding Exterior Work in the Schedule
The roof is a five-day job. In a wet month it can take two weeks, and while the crew waits for dry days the property keeps costing money. A weather buffer turns a vague worry into a number you can budget.
The steps
- List the exterior tasks and their working days (critical path).
- Estimate the share of working days likely to be lost in the season the work will fall in.
- Divide the working days by one minus that share to get the days the work will take.
- Multiply the extra days by your daily holding cost (holding costs).
- Decide whether to move the work, add a buffer or both.
A worked example
Example (illustrative arithmetic, not weather data)
Exterior work totals 15 working days. Holding cost is $300 a week, or $60 a day. Three made-up seasons: dry, with 5% of days lost; wet, with 20% lost; very wet, with 35% lost. Every figure is a made-up round number.
| Season | Share of days lost | Days to finish (15 ÷ (1 − share)) | Extra days | Extra holding cost |
|---|---|---|---|---|
| Dry | 5% | 15.8 | 0.8 | $47 |
| Wet | 20% | 18.75 | 3.75 | $225 |
| Very wet | 35% | 23.1 | 8.1 | $485 |
A wet month adds about 3.75 days and $225. A very wet one adds more than eight days and $485, ten times the dry case (schedule buffer).
The dollars are small compared with a long delay on a bigger project, but the days may matter more than the money if they push the sale into a slower season or past a loan maturity (seasonal log).
Two cheap tools help: plan exterior work for the drier months where you can, and ask the crew to move interior tasks forward when it rains so they are not idle. Put the weather terms in the contract in writing (long-lead items).
Making it routine
- Mark exterior tasks on the schedule and attach a weather buffer to them.
- Keep a record of lost weather days on every job.
- Use your own record next season instead of a guess.
- Ask each contractor how weather delays are handled, in writing.
Run your own numbers
Use the free holding cost calculator below to price the extra days that a weather buffer adds.