Weather Delays: Padding Exterior Work in the Schedule

By DeskTech HQ · · 2 min read

The roof is a five-day job. In a wet month it can take two weeks, and while the crew waits for dry days the property keeps costing money. A weather buffer turns a vague worry into a number you can budget.

The steps

  1. List the exterior tasks and their working days (critical path).
  2. Estimate the share of working days likely to be lost in the season the work will fall in.
  3. Divide the working days by one minus that share to get the days the work will take.
  4. Multiply the extra days by your daily holding cost (holding costs).
  5. Decide whether to move the work, add a buffer or both.

A worked example

Example (illustrative arithmetic, not weather data)

Exterior work totals 15 working days. Holding cost is $300 a week, or $60 a day. Three made-up seasons: dry, with 5% of days lost; wet, with 20% lost; very wet, with 35% lost. Every figure is a made-up round number.

Season Share of days lost Days to finish (15 ÷ (1 − share)) Extra days Extra holding cost
Dry 5% 15.8 0.8 $47
Wet 20% 18.75 3.75 $225
Very wet 35% 23.1 8.1 $485

A wet month adds about 3.75 days and $225. A very wet one adds more than eight days and $485, ten times the dry case (schedule buffer).

The dollars are small compared with a long delay on a bigger project, but the days may matter more than the money if they push the sale into a slower season or past a loan maturity (seasonal log).

Two cheap tools help: plan exterior work for the drier months where you can, and ask the crew to move interior tasks forward when it rains so they are not idle. Put the weather terms in the contract in writing (long-lead items).

Making it routine

  1. Mark exterior tasks on the schedule and attach a weather buffer to them.
  2. Keep a record of lost weather days on every job.
  3. Use your own record next season instead of a guess.
  4. Ask each contractor how weather delays are handled, in writing.

Run your own numbers

Use the free holding cost calculator below to price the extra days that a weather buffer adds.

Quick answers

Why does weather need its own buffer?

Exterior work such as roofing, siding, paint and concrete can only be done in suitable conditions, so some working days are lost. Interior work is mostly unaffected.

How do I estimate lost days?

Use your own records from past jobs in the same season and place, or ask contractors how many days they usually lose. Treat the figure as a range.

Why is the extra time more than the lost share?

Because lost days have to be made up. If one day in five is lost, 15 working days of work takes about 18.75 days to finish, not 18.

Can I reduce the effect?

Sometimes. You can schedule exterior work for the drier part of the year, do interior work during bad weather, or both. Ask your contractor what they can move.

Do the numbers in this guide apply to my project?

No. The share of lost days and the daily cost are made up for the example. They are not weather data or a forecast.