Ask the Contractor to Name a Site Lead and a Backup
The contractor is at another job on Wednesday and the crew has a question about a wall. Nobody answers, so they wait or guess. Asking for a site lead and a backup, with numbers, takes six minutes. The question is how likely an unanswered site question is for the step to pay.
The steps
- Price the step: minutes × the value of your time.
- Price an unanswered question: a crew waiting or guessing for a day.
- Break-even chance = step cost ÷ question cost.
- Walk the site first (walk the site with the contractor before the first draw).
A worked example
Example (illustrative arithmetic, not predictions)
The step takes 6 minutes at $60 an hour: $6. An unanswered question costs $300 in idle or wrong work. Every figure is a made-up round number.
| Chance of an unanswered site question | Expected cost avoided (chance × $300) | Avoided − $6 |
|---|---|---|
| 1% | $3 | −$3 |
| 2% | $6 | $0 (break-even) |
| 5% | $15 | +$9 |
| 8% | $24 | +$18 |
The step pays at a 2% chance of an unanswered question: $6 ÷ $300. Over a multi-week rehab, it is easily exceeded.
Ask for a site lead and a backup, with numbers, write them in the project sheet and say who can approve changes. Put decision authority in the written contract.
Making it routine
- Ask for a site lead and a backup, with numbers.
- Write them in the project sheet.
- Say who can approve changes.
- Put decision authority in the written contract.
Run your own numbers
Use the free holding cost calculator below to see what an idle day costs on your own flip.