Walk the Site With the Contractor Before the First Draw
The contractor’s scope says “kitchen.” The borrower thinks that includes the pantry wall. Midway through, the draw request shows a change order for it. A walk through the site before the first draw, room by room with the scope in hand, clears up gaps. It takes an hour. The question is how likely a scope gap is for the walk to pay.
The steps
- Price the walk: hours × the value of your time.
- Price a scope gap: disputes, change orders and draw delays.
- Break-even chance = walk cost ÷ gap cost.
- Pair it with the kickoff call (kickoff call before the first draw).
A worked example
Example (illustrative arithmetic, not predictions)
The walk takes 1 hour at $60 an hour: $60. A scope gap would cost $1,500. Every figure is a made-up round number.
| Chance of a scope gap without the walk | Expected cost avoided (chance × $1,500) | Avoided − $60 |
|---|---|---|
| 2% | $30 | −$30 |
| 4% | $60 | $0 (break-even) |
| 8% | $120 | +$60 |
| 15% | $225 | +$165 |
The walk pays at a 4% chance of a scope gap: $60 ÷ $1,500. On a full rehab with several trades, gaps are likelier than that.
Bring the scope and the budget, and go room by room asking what is in and what is out. Note differences and have the borrower and contractor settle them in writing before the first draw. Wear the proper footwear and protection, and stay out of the way of the work.
Making it routine
- Bring the scope and the budget.
- Go room by room: what is in, what is out.
- Have differences settled in writing.
- Wear proper protection on site.