Doubling the Crew: Days Saved vs Extra Labor Cost

By DeskTech HQ · · 2 min read

The painters say two people will take ten days. You could ask for four. Would it take five? Almost never. Work does not divide that neatly, and the extra people cost money. The question is whether the days saved are worth the extra labor.

The steps

  1. Count worker-days at the base crew: workers times days.
  2. Ask how long a bigger crew would take.
  3. Count worker-days at the bigger crew, and subtract to find the extra labor. Price it at the day rate.
  4. Find the days saved and multiply by your holding cost per day (holding costs).
  5. Compare the two.

A worked example

Example (illustrative arithmetic, not standards)

A crew of 2 takes 10 days: 20 worker-days. A worker-day costs $250. Your holding cost is $150 a day. Four workers might take 6 days, or 5, or somewhere between. Every figure is a made-up round number.

Net = days saved × $150 − extra worker-days × $250.

Days the crew of 4 takes Worker-days Extra worker-days Days saved (× $150) Extra labor (× $250) Net
6 24 4 $600 $1,000 −$400
5.65 22.6 2.6 $653 $650 $0
5.5 22 2 $675 $500 +$175
5 20 0 $750 $0 +$750

If four workers get the job done in five days with no waste, doubling the crew is free and saves $750. If they take six days because they bump into each other, it costs $400 net. The break-even is about 5.65 days. A perfect split is rare, so expect the middle rows.

The result also depends on the work. Painting a large open house divides well among workers. Tile in one bathroom does not. A task on the critical path, where nothing else can start until it is done, is worth speeding up. A task off the critical path saves nothing, because the schedule is waiting on something else (overlapping trades). And if the contractor prices the job as a lump sum, the question becomes what a faster schedule costs, not what the extra workers cost (rush fees).

Making it routine

  1. Know which tasks are on the critical path.
  2. Ask for a price for a faster schedule on those only.
  3. Compare the days saved with the extra cost.
  4. Record how long bigger crews actually took.

Run your own numbers

Use the free holding cost calculator below to find the value of each day saved.

Quick answers

Does doubling the crew halve the time?

Usually not. Workers get in each other's way, tasks have a sequence, and supervision takes time.

How do I decide whether a bigger crew pays?

Compare the holding cost of the days saved with the extra worker-days of labor you would pay for.

What is a worker-day?

One person working one day. A crew of 4 working 6 days is 24 worker-days.

Does the contractor decide crew size?

Often, and the price is usually for the job, not by the day. Ask what a faster schedule would cost.

Do the numbers in this guide apply to my project?

No. The crew sizes, days and rates are made up for the example. They are not standards.

Keep reading

Flip project management

Overlapping Trades: Days Saved vs Rework Risk

Learn how to weigh the days saved by letting two trades work at once against the chance that one damages the other's work, and the odds that favor it.

· 2 min read
Flip project management

Budget Check Frequency: Weekly or Monthly?

Learn how to compare the extra time a weekly rehab budget check takes with the overrun it can catch weeks sooner, and the odds that make weekly worthwhile.

· 2 min read

This guide is general education, not legal, tax, or financial advice. Talk with a licensed professional about your situation.