Doubling the Crew: Days Saved vs Extra Labor Cost
The painters say two people will take ten days. You could ask for four. Would it take five? Almost never. Work does not divide that neatly, and the extra people cost money. The question is whether the days saved are worth the extra labor.
The steps
- Count worker-days at the base crew: workers times days.
- Ask how long a bigger crew would take.
- Count worker-days at the bigger crew, and subtract to find the extra labor. Price it at the day rate.
- Find the days saved and multiply by your holding cost per day (holding costs).
- Compare the two.
A worked example
Example (illustrative arithmetic, not standards)
A crew of 2 takes 10 days: 20 worker-days. A worker-day costs $250. Your holding cost is $150 a day. Four workers might take 6 days, or 5, or somewhere between. Every figure is a made-up round number.
Net = days saved × $150 − extra worker-days × $250.
| Days the crew of 4 takes | Worker-days | Extra worker-days | Days saved (× $150) | Extra labor (× $250) | Net |
|---|---|---|---|---|---|
| 6 | 24 | 4 | $600 | $1,000 | −$400 |
| 5.65 | 22.6 | 2.6 | $653 | $650 | $0 |
| 5.5 | 22 | 2 | $675 | $500 | +$175 |
| 5 | 20 | 0 | $750 | $0 | +$750 |
If four workers get the job done in five days with no waste, doubling the crew is free and saves $750. If they take six days because they bump into each other, it costs $400 net. The break-even is about 5.65 days. A perfect split is rare, so expect the middle rows.
The result also depends on the work. Painting a large open house divides well among workers. Tile in one bathroom does not. A task on the critical path, where nothing else can start until it is done, is worth speeding up. A task off the critical path saves nothing, because the schedule is waiting on something else (overlapping trades). And if the contractor prices the job as a lump sum, the question becomes what a faster schedule costs, not what the extra workers cost (rush fees).
Making it routine
- Know which tasks are on the critical path.
- Ask for a price for a faster schedule on those only.
- Compare the days saved with the extra cost.
- Record how long bigger crews actually took.
Run your own numbers
Use the free holding cost calculator below to find the value of each day saved.