Rush Fees: Paying to Finish a Rehab Faster

By DeskTech HQ · · 2 min read

A contractor offers to add a second crew for $1,800 and finish twelve days sooner. Is that a bargain or a gift? The answer is a division: the fee over what each day of waiting costs you.

The steps

  1. Total your monthly holding costs and divide by 30 to get a cost per day (holding costs on a flip).
  2. Get the rush fee and the days it is meant to save, in writing.
  3. Divide the fee by the cost per day. That is the break-even number of days.
  4. Compare it with the days saved you can honestly expect, and discount for the chance of slippage.
  5. Weigh what the arithmetic leaves out: quality, rework and sale timing.

A worked example

Example (illustrative arithmetic, not market data)

Holding costs run $4,500 a month, so $4,500 ÷ 30 = $150 a day. The rush fee is $1,800 for a promised saving of 12 days. Every figure is a made-up round number.

Days actually saved Holding cost saved (× $150) Rush fee Net
8 $1,200 $1,800 −$600
12 $1,800 $1,800 $0
18 $2,700 $1,800 +$900
Break-even $1,800 ÷ $150 = 12 days

The fee breaks even only if all 12 promised days are saved. A job that saves 8 loses $600. Because the promise is the break-even point, the deal has no cushion: any slippage costs you. Ask for a fee tied to the date, so that you pay for days actually saved (contractor payment schedule and change orders).

The arithmetic also leaves out the cost of a rushed job: more rework, less careful finish work and a harder time with inspections. A fee that only breaks even on paper is a poor trade once those are counted (rehab schedule buffer).

Making it routine

  1. Know your cost per day before the work starts.
  2. Ask for any rush fee in writing, as a change order.
  3. Tie the fee to the date it buys.
  4. After the job, record the days actually saved.

Run your own numbers

Use the free holding cost calculator below to see what a day of delay costs on your project.

Quick answers

When does a rush fee make sense?

When the holding cost of the days it saves is larger than the fee. Divide the fee by the holding cost per day to find the days it must save.

What goes into the holding cost per day?

Loan interest, taxes, insurance, utilities and other costs that run while you own the property, divided by the days in the period.

What does the arithmetic leave out?

Quality, the chance of rework, and the effect of timing on the sale price. A rushed job can cost more than it saves.

How should I agree to a rush fee?

In writing, as a change order that states the fee, the date it is meant to achieve and what happens if the date is missed. Check contract and lien rules in your state with a qualified professional.

Do the numbers in this guide apply to my project?

No. The holding cost, fee and days saved are made up for the example. They are not quotes or market data.

Keep reading

Flip project management

Drying Time Before Flooring: Wait or Rush?

Learn how to weigh the holding cost of waiting for a subfloor to dry against the chance of flooring failure if you rush, and the odds that favor waiting.

· 2 min read

This guide is general education, not legal, tax, or financial advice. Talk with a licensed professional about your situation.