Pressure-Test the Plumbing Before the Drywall Goes Up
A joint that is not quite tight shows up when the pipes are under pressure. If the walls are open, a plumber tightens it in minutes. If the walls are closed, the same leak means opening drywall, drying the cavity and repainting. A test before closing costs little. The question is how likely a leak has to be to justify it.
The steps
- Price a pressure test, whether done by your plumber, as part of the rough-in inspection or by an extra visit.
- Price a leak found after the walls close: opening, drying, repair, repaint and delay (holding costs).
- Divide the test price by the leak cost. That is the break-even chance of a leak.
- Compare it with how often new plumbing on your projects has leaked.
- Test before the inspection and before the walls close (as-built photos).
A worked example
Example (illustrative arithmetic, not quotes)
A test costs $150. A leak behind a closed wall costs about $4,000 to find, open, dry, repair and repaint. Every figure is a made-up round number.
| Chance a joint leaks | Expected cost avoided (× $4,000) | Test cost | Net |
|---|---|---|---|
| 1% | $40 | $150 | −$110 |
| 3.75% | $150 | $150 | $0 |
| 10% | $400 | $150 | +$250 |
| Break-even | $150 ÷ $4,000 = 3.75% |
If about one new plumbing job in twenty-seven has a leaking joint, the test pays. With extensive new plumbing, such as a full repipe or two new bathrooms, the number of joints is large, and a leak somewhere is much more likely than for a single fixture. For a simple fixture swap, it is less so.
If your plumber already pressure-tests as part of the job, or the rough-in inspection includes it, you may not need a second test, but make sure the test happened, and ask for the result. Keep the pressure held for the time the plumber or the code specifies. Then take your photos and close the walls (rehab permits and inspections).
Making it routine
- Confirm that a pressure test is on the schedule before the drywall.
- Ask for the result and the hold time.
- Photograph the open walls after the test.
- Record any leak found and where.
Run your own numbers
Use the free holding cost calculator below to see what a delay from a leak costs on your project.