Change Orders: Price Them Before the Work, Not After
Midway through the job the contractor finds something and says, “I’ll take care of it.” That sentence is how a budget quietly doubles. If the price is agreed before the work, you can compare it, negotiate it or choose a different path. If it is agreed after, you pay what you are asked.
The steps
- Require every change to be written and signed before work on it starts.
- State the work, the price and the effect on the schedule.
- Compare the price with another bid when it is large.
- Keep a log of change orders against the budget.
- Total the difference between what you agreed and what you would have been billed (contractor payment schedule and change orders).
A worked example
Example (illustrative arithmetic, not quotes)
A project has 8 changes. Priced before the work they average $800; the same work billed after the fact averages $1,100. Writing each one up takes 10 minutes (about $10). Every figure is a made-up round number.
| Number of change orders | Saving ($300 each) | Cost of writing them up ($10 each) | Net |
|---|---|---|---|
| 4 | $1,200 | $40 | +$1,160 |
| 8 | $2,400 | $80 | +$2,320 |
| 12 | $3,600 | $120 | +$3,480 |
On these numbers, pricing before the work saves $300 a change, a 27% difference, for ten minutes of writing. Whatever the exact figure in your market, the direction is consistent: a price agreed after the fact tends to be higher, because the contractor already has the work in hand and you have no alternative.
Written change orders protect both sides. They record what was agreed, so there is less to argue about later. They make the budget visible, since you can see the total of change orders as they accumulate. And in many places the law expects them for changes over a certain size. Whether a change order affects your contract’s price, payment terms or lien rights depends on the contract and state law, so have an attorney review your form (contingency burn).
Making it routine
- Do not let work start on a change without a signed order.
- Keep a running total against the budget.
- Get a second price on large changes.
- Have an attorney review your contract and change order form.