Put the Final Walkthrough Date on the Calendar at the Start

By DeskTech HQ · · 1 min read

The rehab is nearly done, but nobody scheduled the final walkthrough, so the punch list starts a week later than it could. Putting a target date on the calendar when the rehab starts takes three minutes. The question is how likely a late walkthrough is for the step to pay.

The steps

  1. Price the step: minutes × the value of your time.
  2. Price a late walkthrough: days of carry while punch items wait to be found.
  3. Break-even chance = step cost ÷ delay cost.
  4. Plan the final draw too (a written final draw checklist).

A worked example

Example (illustrative arithmetic, not predictions)

The step takes 3 minutes at $60 an hour: $3. A late walkthrough costs $300 in carry. Every figure is a made-up round number.

Chance of a late walkthrough Expected cost avoided (chance × $300) Avoided − $3
0.5% $1.50 −$1.50
1% $3 $0 (break-even)
3% $9 +$6
5% $15 +$12

The step pays at a 1% chance of a late walkthrough: $3 ÷ $300. On a flip with a tight schedule, it is easily exceeded.

Put a target date on the calendar with a reminder two weeks before, tell the contractor and move it if the schedule moves.

Making it routine

  1. Put a target date on the calendar at the start.
  2. Set a reminder two weeks before.
  3. Tell the contractor.
  4. Move it if the schedule moves.

Run your own numbers

Use the free holding cost calculator below to see what a late week costs on your own flip.

Quick answers

What do you put on the calendar?

A target date for the final walkthrough, with a reminder two weeks before.

How do I price it?

The minutes to set the date and reminder times the value of your time.

What does a late walkthrough cost?

Days of carry while punch items wait to be found.

What is the break-even chance?

The step's cost divided by that cost.

Do the numbers in this guide apply to my flip?

No. The costs and odds are made up for the example. They are not predictions.

Keep reading

Flip project management

Ask for a Photo of Each Delivered Material Pallet

Learn how to price asking the contractor for a photo of each delivered material pallet and find the short-shipment chance at which two minutes pays.

· 1 min read

This guide is general education, not legal, tax, or financial advice. Talk with a licensed professional about your situation.