Ask Which Inspections Each Permit Needs Before You Start
The drywall goes up before the framing inspection. The inspector makes you open three walls. A ten-minute call before the work starts asks which inspections each permit needs and when. The question is how likely a failed or missed inspection is for the call to pay.
The steps
- Price the call: minutes × the value of your time.
- Price a failed or missed inspection: opening work, rework and delay.
- Break-even chance = call cost ÷ cost of a failed inspection.
- Photograph the permit too (photo of the posted permit at the first draw).
A worked example
Example (illustrative arithmetic, not predictions)
The call takes 10 minutes at $60 an hour: $10. A failed or missed inspection costs $400. Every figure is a made-up round number.
| Chance of a failed or missed inspection | Expected cost avoided (chance × $400) | Avoided − $10 |
|---|---|---|
| 1.25% | $5 | −$5 |
| 2.5% | $10 | $0 (break-even) |
| 5% | $20 | +$10 |
| 10% | $40 | +$30 |
The call pays at a 2.5% chance of a failed or missed inspection: $10 ÷ $400. On a rehab with several permits, it is plausible.
Ask which inspections each permit needs, what must be visible at each stage, how far ahead to book and who to call. Write the list on the schedule and share it with the crew.
Making it routine
- Ask which inspections are needed and at what stage.
- Ask what must be visible at each stage.
- Ask how far ahead to book.
- Share the list with the crew.
Run your own numbers
Use the free BRRRR calculator below to see what a delay from rework costs on your own hold.