Baseline Photos at Closing: The Condition Dispute Odds
Midway through a rehab, a draw request claims a repair that you believe was already done at closing. Without photos from the start, you cannot say. A set of baseline photos costs five minutes to file and review. The question is how likely a condition dispute is for the step to pay.
The steps
- Price the review: minutes × the value of your time.
- Estimate the cost of a dispute over pre-existing condition.
- Break-even chance = cost ÷ dispute cost.
- Pair it with the as-built photos (as-built photos before the walls close).
A worked example
Example (illustrative arithmetic, not predictions)
The review takes 5 minutes at $60 an hour: $5. A condition dispute would cost $500. Every figure is a made-up round number.
| Chance of a condition dispute | Expected cost avoided (chance × $500) | Avoided − $5 |
|---|---|---|
| 0.5% | $2.50 | −$2.50 |
| 1% | $5.00 | $0 (break-even) |
| 3% | $15.00 | +$10.00 |
| 6% | $30.00 | +$25.00 |
The baseline pays at a 1% chance of a dispute: $5 ÷ $500. On a rehab with scope questions, that is likely exceeded.
Ask the borrower for dated photos of every room and the exterior at closing, file them with the loan, and compare them with draw photos. Make sure the loan documents let you request them, and keep the photos with the other loan records.
Making it routine
- Ask for baseline photos at closing.
- File them with the loan.
- Compare them with draw photos.
- Check the documents for your right to request them.
Run your own numbers
Use the free fix-and-flip loan sizer below to see how a disputed draw changes the funds left for a rehab.