Contingency Burn: Used vs Percent Complete

By DeskTech HQ · · 2 min read

A contingency is meant to last until the work is done. A common way to find out too late that it will not is to look at it only at the end. The question to ask each week is simple: have we used a bigger share of the contingency than the share of the work we have finished?

The steps

  1. Set the contingency (for example, a share of the budget) (contingency sizing by risk).
  2. At each check, record the contingency used and the share of the work complete.
  3. Divide used by percent complete. That is the projected total use at the same pace.
  4. Compare it with the contingency you set.
  5. If it runs over, act while choices remain (weekly scorecard).

A worked example

Example (illustrative arithmetic, not benchmarks)

A $60,000 rehab has a 10% contingency: $6,000. Three check-ins. Every figure is a made-up round number.

Work complete Contingency used Share of contingency used Projected total at this pace Vs $6,000
20% $600 10% $3,000 Under by $3,000
40% $3,500 58% $8,750 Over by $2,750
60% $4,800 80% $8,000 Over by $2,000

At 20% complete the project looks healthy. By 40% the contingency is 58% spent on 40% of the work, and at that pace it ends $2,750 over. At 60% the pace has eased, but the projection still runs $2,000 over. Seeing this at 40%, with 60% of the work still to come, gives you time to act. Seeing it at 95% does not.

Early work is often the riskiest: demolition finds rot, wiring and plumbing surprises, so a high burn early may not repeat. The projection is a warning, not a forecast. What it should trigger is a look at the remaining scope: what can be simplified, what can be bid more tightly, and what finish choices still have room (fixture allowances).

Making it routine

  1. Record used and percent complete at every weekly check.
  2. Compute the projection each time.
  3. Review remaining scope when it runs over.
  4. Record how the final contingency compared with the projections.

Run your own numbers

Use the free MAO calculator below to see how a larger rehab cost changes the most you can offer next time.

Quick answers

What is contingency burn?

How quickly a rehab contingency is being used, compared with how much of the work is done.

How do I project the final contingency use?

Divide the contingency used so far by the share of the work completed. That is the pace if the rest of the job goes the same way.

What if early work is the riskiest?

Then the projection overstates the later use, since demolition often finds the surprises. Adjust, but do not ignore the signal.

What should I do when the projection runs over?

Look for savings, simplify remaining scope or accept a lower profit knowingly, while you can still choose.

Do the numbers in this guide apply to my project?

No. The budget, spending and progress are made up for the example. They are not benchmarks.

Keep reading

Rehab budgeting

GC Markup vs Managing the Trades Yourself

Learn how to compare a general contractor's markup with the hours and mistakes of managing the trades yourself, and when self-management costs more.

· 2 min read
Rehab budgeting

Pre-Offer Contractor Walk-Through: Worth the Fee?

Learn how to weigh the cost of a paid contractor walk-through before you offer against the rehab estimate error it can catch, and the odds that favor it.

· 2 min read

This guide is general education, not legal, tax, or financial advice. Talk with a licensed professional about your situation.