Contractor Payment Schedules and Change Orders
A rehab usually goes wrong on paper before it goes wrong on site. A payment schedule that follows finished work and a habit of writing changes down protect the budget, the schedule and the relationship with the contractor.
A payment schedule that follows the work
- Deposit. A modest amount at signing.
- Stage payments. Paid when named stages are complete and inspected.
- Final payment. Held until the work is complete, required inspections pass and any releases are in hand (permits and inspections).
The payment steps should match the scope of work, line by line (how to write a scope of work).
A worked example
Example (illustrative arithmetic, not market data)
Assume a $40,000 contract. The percentages are made up for the example and are not a standard. Every figure is a made-up round number.
| Payment | Share | Calculation | Amount |
|---|---|---|---|
| Deposit at signing | 10% | 10% × $40,000 | $4,000 |
| Rough-in complete | 30% | 30% × $40,000 | $12,000 |
| Drywall complete | 30% | 30% × $40,000 | $12,000 |
| Substantial completion | 20% | 20% × $40,000 | $8,000 |
| Final, after sign-offs | 10% | 10% × $40,000 | $4,000 |
| Total | 100% | $40,000 |
After drywall, the contractor finds a rotted subfloor and a signed change order adds $2,400.
| Item | Calculation | Amount |
|---|---|---|
| Paid so far | $4,000 + $12,000 + $12,000 | $28,000 |
| New contract total | $40,000 + $2,400 | $42,400 |
| Still to pay | $42,400 − $28,000 | $14,400 |
| Contingency left | 10% × $40,000 = $4,000, less $2,400 | $1,600 |
The change order is paid from the contingency, and the budget and the agreement still match (per square foot vs line item).
A checklist
- Tie every payment to a named stage, not a date.
- Write each change down, price it and sign it before the work starts.
- Update the budget the day a change order is signed.
- Keep copies of the agreement, change orders, inspection results and any releases in the project file (flip project checklist).
- Pay the final amount only after the closeout items are done.