Concrete Pump or Wheelbarrow? The Cubic Yards That Cross

By DeskTech HQ · · 1 min read

Concrete arrives by truck and has to get to the forms before it sets. A wheelbarrow crew moves it by hand. A pump truck moves it through a hose. The pump has a fixed charge plus a price per yard. The two cross at a volume.

The steps

  1. Get the pump’s fixed charge and per-yard price.
  2. Estimate the labor cost per yard to wheel the mix.
  3. Crossing yards = pump fixed charge ÷ (labor per yard − pump per-yard price).
  4. Compare with the size of the pour (doubling the crew).

A worked example

Example (illustrative arithmetic, not quotes)

The pump costs $650 plus $20 a yard. Moving a yard by wheelbarrow costs $95 in labor. Every figure is a made-up round number.

Yards poured Pump ($650 + $20 × yards) Wheelbarrow ($95 × yards) Cheaper
4 $730 $380 Wheelbarrow, by $350
8.7 $823 $823 Even
15 $950 $1,425 Pump, by $475

The pump wins above about nine yards: $650 ÷ ($95 − $20). A small pad is a wheelbarrow job. A driveway or a slab is a pump job.

The table understates the pump for hard pours. If the truck cannot get close, or the pour is uphill, or the mix has to be placed fast, the labor per yard rises, and the crossing falls. Ask the concrete supplier and the pump operator before the pour (renting or buying tools).

Making it routine

  1. Measure the pour in cubic yards.
  2. Get a pump quote with its minimum charge.
  3. Compute the crossing volume.
  4. Plan access for the truck and the hose.

Run your own numbers

Use the free holding cost calculator below to see what a day of pour delay costs.

Quick answers

Where do they cross?

At the pump's fixed charge divided by the labor cost per yard saved.

When is a pump useful?

When the pour is large or hard to reach.

What else changes the answer?

The distance from truck to pour, the slope and how fast the mix must be placed.

Who should place concrete?

Licensed trades where required, with permits and inspections.

Do the numbers in this guide apply to my project?

No. The costs are made up for the example. They are not quotes.

Keep reading

Flip project management

Builder's Risk: Per Project or Annual Policy?

Learn how to find the number of rehab projects a year at which an annual builder's risk policy costs less than buying one policy per project.

· 1 min read

This guide is general education, not legal, tax, or financial advice. Talk with a licensed professional about your situation.