Reviewing a Draw Request: A Lender's Checklist and Red Flags
A construction holdback is a promise to pay for work as it is finished. Each draw request is a check on that promise: has the work happened, is it paid for, and is there enough left to finish.
A review checklist
- Match the request to the budget. Each line should be in the approved budget (how a draw schedule works).
- Inspect the work. Compare what is claimed with what is there, line by line.
- Check the paperwork. Invoices, and lien waivers or releases if the documents or the state call for them.
- Apply retainage. Hold the agreed percentage.
- Check what is left. Make sure the undrawn holdback covers the remaining work.
- Record it. Add the draw to the ledger and the loan file (ledger reconciliation).
A worked example
Example (illustrative arithmetic, not market data)
Assume a $60,000 holdback, a first draw request of $18,000, and 10% retainage. The 10% is an assumption for the example. Every figure is a made-up round number.
| Budget line | Requested | Inspected as complete | Supported amount |
|---|---|---|---|
| Electrical, $10,000 line | $10,000 | 60% | 60% × $10,000 = $6,000 |
| Plumbing, $8,000 line | $8,000 | 100% | $8,000 |
| Total | $18,000 | $14,000 |
| Step | Calculation | Amount |
|---|---|---|
| Unsupported part of the request | $18,000 − $14,000 | $4,000 |
| Retainage held | 10% × $14,000 | $1,400 |
| Funded now | $14,000 − $1,400 | $12,600 |
| Holdback left to draw | $60,000 − $14,000 | $46,000 |
The lender funds $12,600 instead of $18,000, and holds $1,400 until completion. The electrical line shows the gap an inspection is there to find.
Red flags
- A request larger than the inspected work.
- Lines that run ahead of the schedule.
- Missing invoices, or invoices from unfamiliar vendors.
- Scope changes with no written approval (contractor payments and change orders).
- Pressure to fund quickly with no inspection.
- A remaining holdback that no longer covers the remaining work.
What to do with a gap
Fund what is supported, explain the rest in writing, and note when the borrower may resubmit. Keep the inspection report and the explanation in the loan file (what a lender tracks after closing).