Paying to Hold a Backup Crew: Is It Worth It?

By DeskTech HQ · · 2 min read

The framing crew is booked to start Monday. If they do not show, it may take a week to find another, and that week costs you holding costs. A second crew will hold the date for a fee. The question is how likely a no-show has to be for the fee to be worth paying.

The steps

  1. Find your holding cost per day (holding costs).
  2. Estimate the days lost to a no-show without a backup, and with one.
  3. The days saved times the daily cost is the saving from having a backup.
  4. Divide the standby fee by that saving. That is the break-even chance of a no-show.
  5. Compare it with the first crew’s record.

A worked example

Example (illustrative arithmetic, not statistics)

Holding cost is $150 a day. A no-show with no backup costs 7 days to replace the crew: $1,050. With a backup, it costs 1 day: $150. The backup saves $900 when it is needed. The standby fee is $300. Every figure is a made-up round number.

Chance the first crew does not show Expected saving (× $900) Standby fee Net
10% $90 $300 −$210
33.3% $300 $300 $0
50% $450 $300 +$150
Break-even $300 ÷ $900 = 33.3%

The fee pays only if there is about a one-in-three chance of a no-show. For a crew you have used before with a good record, the chance is far lower, and the fee is not worth it. For a new crew with no references, or at a time of year when everyone is booked, it may be much higher.

Cheaper paths often do better. Get two bids at the start and keep a relationship with the second crew, so that a replacement is a phone call and not a search. And vet the first crew: licensed, insured, with references you have called (contractor insurance and license check). The fee is a patch for a risk that screening can reduce.

Making it routine

  1. Keep a record of each crew’s reliability.
  2. Vet new crews before the start date.
  3. Keep a second bid on file for key trades.
  4. Pay a standby fee only when the first crew is untested.

Run your own numbers

Use the free holding cost calculator below to find the cost of each day of delay.

Quick answers

What is a standby fee?

A payment to a second contractor to keep a start date open for you in case the first one does not show.

How do I decide whether to pay it?

Compare the fee with the days the backup saves, at your holding cost per day, times the chance the first crew fails to show.

Are there cheaper ways to get a backup?

Yes. A good relationship with a second contractor, a deposit that is credited to the job, or a bid from two crews at the start.

Does the first crew's record matter?

A great deal. A crew you know is reliable has a low chance of a no-show, which lowers the case for paying.

Do the numbers in this guide apply to my project?

No. The fee, days and odds are made up for the example. They are not statistics.

Keep reading

Flip project management

Pre-Inspection Dry Run vs a Failed Inspection

Learn how to weigh an hour spent walking the job before a final inspection against the re-inspection fee and delay of a failure, and when it pays.

· 2 min read
Flip project management

Budget Check Frequency: Weekly or Monthly?

Learn how to compare the extra time a weekly rehab budget check takes with the overrun it can catch weeks sooner, and the odds that make weekly worthwhile.

· 2 min read

This guide is general education, not legal, tax, or financial advice. Talk with a licensed professional about your situation.