Pre-Inspection Dry Run vs a Failed Inspection
A final inspection that fails means another appointment, another fee in some places, and days of waiting while the clock on your holding costs keeps running. An hour walking the job first, with the inspector’s list, costs far less. The question is how often a failure has to be likely to justify it.
The steps
- Value an hour of your time, or your contractor’s, for the dry run.
- Find the cost of a failure: any re-inspection fee plus the days to the next appointment times your holding cost per day (holding costs).
- Divide the dry run’s cost by the failure cost. That is the break-even chance of a failure.
- Compare it with how often your inspections have failed.
- Use the inspector’s own checklist for the dry run (permits and inspections).
A worked example
Example (illustrative arithmetic, not standards)
The dry run takes 1 hour at $60. A failed inspection costs a $75 re-inspection fee plus 5 days to the next slot at $150 a day: $75 + $750 = $825. Every figure is a made-up round number.
| Chance of failing without a dry run | Expected failure cost (× $825) | Dry run | Net |
|---|---|---|---|
| 5% | $41 | $60 | −$19 |
| 7.3% | $60 | $60 | $0 |
| 20% | $165 | $60 | +$105 |
| Break-even | $60 ÷ $825 = 7.3% |
If your final inspections fail more than about one time in fourteen, a dry run pays. For many flips the real failure rate on a first try is higher than that, especially where items such as smoke alarms, handrails, electrical covers or permits left open are common reasons. The dry run’s value rises with the cost of a day of delay and with the length of the wait for a re-inspection.
Keep a list of what failed on past projects. After a few, the same items appear again, and a standing pre-inspection checklist built from that list is better than any general one (weekly checklist).
Making it routine
- Ask the building department what the final inspection covers.
- Build a pre-inspection checklist from past failures.
- Do the dry run the day before the inspection.
- Record every failure and its reason.
Run your own numbers
Use the free holding cost calculator below to find the cost of each day of waiting for a re-inspection.