Save Every Permit Final Sign-Off in the Property Folder
A refinance appraiser or a buyer’s agent finds an open permit from three years ago on the city site. The work passed, but nobody kept the sign-off. Scanning each sign-off into the property folder takes five minutes. The question is how likely an unproven permit is for the step to pay.
The steps
- Price the step: minutes × the value of your time.
- Price an unproven permit: a hunt for records and a delay.
- Break-even chance = step cost ÷ unproven-permit cost.
- Photograph the posted permit too (photo of the posted permit at the first draw).
A worked example
Example (illustrative arithmetic, not predictions)
The step takes 5 minutes at $60 an hour: $5. An unproven permit costs $500 to clear. Every figure is a made-up round number.
| Chance of an unproven permit | Expected cost avoided (chance × $500) | Avoided − $5 |
|---|---|---|
| 0.5% | $2.50 | −$2.50 |
| 1% | $5 | $0 (break-even) |
| 3% | $15 | +$10 |
| 6% | $30 | +$25 |
The step pays at a 1% chance of an unproven permit: $5 ÷ $500. With several permits across a rehab, it is plausible.
When an inspector signs off, photograph or scan the card or the city record the same day, name the file with the permit number and date and check the city site a month later to confirm it shows closed.
Making it routine
- Photograph or scan the sign-off the same day.
- Name the file with permit number and date.
- Check the city site a month later.
- Ask the building department about any that show open.
Run your own numbers
Use the free BRRRR calculator below to see what a delay at refinance costs on your own hold.