Send Every Bidder the Same Written Scope on One Bid Sheet
Three bids arrive in three formats. The cheapest leaves out demolition and permits, and the change orders start in week two. One bid sheet with the same scope for everyone takes twenty minutes to build. The question is how likely an apples-to-oranges bid is for the sheet to pay.
The steps
- Price the sheet: minutes × the value of your time.
- Price an apples-to-oranges bid: the change order for what was left out.
- Break-even chance = sheet cost ÷ change-order cost.
- Think about which bid to pick (lowest bid or middle bid).
A worked example
Example (illustrative arithmetic, not predictions)
The sheet takes 20 minutes at $60 an hour: $20. An apples-to-oranges bid costs $800 in change orders. Every figure is a made-up round number.
| Chance of an apples-to-oranges bid | Expected cost avoided (chance × $800) | Avoided − $20 |
|---|---|---|
| 1.25% | $10 | −$10 |
| 2.5% | $20 | $0 (break-even) |
| 5% | $40 | +$20 |
| 8% | $64 | +$44 |
The sheet pays at a 2.5% chance of an apples-to-oranges bid: $20 ÷ $800. With several bids on a rehab, it is likely.
List the scope line by line, including demolition, permits and cleanup, ask each bidder to price every line and say what is excluded, and compare totals only after the lines match.
Making it routine
- List the scope line by line.
- Include demolition, permits and cleanup.
- Ask for a price on every line and exclusions.
- Compare totals only when lines match.
Run your own numbers
Use the free holding cost calculator below to see what a week of change-order delay costs on your own flip.