Setting a Flip Goal: Back-Solve Deals, Days and Cash
A goal like “make $100,000 this year” sounds like a number. It is really a chain of numbers: how many deals, how long they take, and how much cash is out at the same time. Working back through the chain shows whether the goal fits the business.
The steps
- Deals needed = goal ÷ average actual profit per project.
- Project-days = deals × average days held.
- Projects running at once = project-days ÷ 365.
- Cash needed = projects at once × cash per project, plus a reserve for each (cash reserve).
A worked example
Example (illustrative arithmetic, not a prediction)
Use the year-end review of four projects: actual profit of $87,620 over 660 days, an average of $21,905 a project and 165 days (year-end flip review). The goal is $100,000. Cash per project is $80,280 and the cushion is $7,120 (flip profit and ROI). Every figure is a made-up round number.
| Step | Calculation | Result |
|---|---|---|
| Average actual profit per project | $87,620 ÷ 4 | $21,905 |
| Deals needed | $100,000 ÷ $21,905 = 4.57, rounded up | 5 |
| Total project-days | 5 × 165 | 825 |
| Projects running at once | 825 ÷ 365 = 2.26, rounded up | 3 |
| Cash tied up | 3 × $80,280 | $240,840 |
| Reserves | 3 × $7,120 | $21,360 |
| Cash needed at once | $240,840 + $21,360 | $262,200 |
Five average projects would earn 5 × $21,905 = $109,525, a little above the goal. To run them in a year, about three must be under way at the same time, which needs about $262,200 of cash or financing available.
What to do with the answer
- Compare it with the cash you actually have.
- If it is short, test the choices in dollars: fewer or bigger deals, shorter projects, borrowed money or partners (compare the cost of capital).
- Test the plan at a lower average profit (break-even price).
- Write the goal, the steps and the assumptions down and revisit them in a quarter.
Run your own numbers
Use the free holding cost calculator below to see how project length changes the cost of carrying several projects at once.