How Much Cash Reserve to Keep on a Flip
A flip can be profitable on paper and still fail on cash. The deal is not usually lost when the profit shrinks; it is lost when there is no money to pay for the next bill.
Two layers of cushion
- Contingency. Inside the rehab budget, for repair costs nobody has found yet (rehab estimates).
- Reserve. Outside the budget, for delays, overruns and timing problems.
A worked example
Example (illustrative arithmetic, not market data)
Use the project from the profit and ROI guide: total cost of $194,280 with $80,280 of the investor’s own cash (flip profit and ROI). Monthly carrying costs are $1,560 (price cut or wait). The two extra months and the 10% contingency are assumptions. Every figure is a made-up round number.
| Item | Calculation | Amount |
|---|---|---|
| Two extra months of carrying costs | 2 × $1,560 | $3,120 |
| Contingency on the $40,000 rehab | 10% × $40,000 | $4,000 |
| Cushion to hold | $3,120 + $4,000 | $7,120 |
| Share of total cost | $7,120 ÷ $194,280 | 3.7% |
| Share of the investor’s cash | $7,120 ÷ $80,280 | 8.9% |
| Cash needed to start | $80,280 + $7,120 | $87,400 |
The investor needs $87,400 on hand to carry a project that shows $80,280 of cash in the budget. If only $80,280 is available, the first surprise forces a choice between borrowing on poor terms and stopping work.
How to use it
- Add the cushion to the cash plan before you offer, not after.
- Hold it in an account separate from the project money.
- Replenish or release it as the project reaches milestones (contractor payments).
- Check what a lender or partner expects for reserves (personal guarantees and recourse).
- Walk away from a deal that works only if nothing goes wrong (break-even price).
Run your own numbers
Use the free holding cost calculator below to see what extra months cost on your project.