Subcontractor Pay Terms: What Net 7 vs Net 30 Is Worth
A contractor quotes $40,000 if you pay within 7 days and $41,200 if you pay in 30. The difference looks like a fee for patience. Whether it is a good deal depends on what 23 days of your cash costs.
The steps
- Get both prices in writing: the fast-pay price and the slow-pay price.
- Find the number of days between the two payment dates.
- Value your cash at what it costs you per year, such as your loan rate.
- Compute the cost of paying early: bid × rate × days ÷ 365.
- Compare with the price difference (early-pay discounts).
A worked example
Example (illustrative arithmetic, not quotes)
The bid is $40,000 at net 7 or $41,200 at net 30, a premium of 3%. Your cash costs 12% a year. Paying 23 days sooner costs $40,000 × 12% × 23 ÷ 365 = $302. Every figure is a made-up round number.
| Premium the contractor charges for slow pay | Premium in dollars (× $40,000) | Cost of paying 23 days sooner | Cheaper option |
|---|---|---|---|
| 0.5% | $200 | $302 | Net 30, by $102 |
| 0.76% | $302 | $302 | Equal |
| 3% | $1,200 | $302 | Net 7, by $898 |
| Break-even | $302 ÷ $40,000 = 0.76% |
At a 3% premium, paying fast saves $898. Even at a 1% premium it would save. The cost of cash for 23 days is only about three-quarters of one percent of the bid, so most slow-pay premiums are larger than that. If a contractor offers you a real discount for fast payment, take it.
The condition is that fast pay must follow completed work. Paying quickly for work that is not done gives away your best protection. Tie payment to inspected milestones, and keep a final amount back until the work is finished and lien rights are cleared (contractor payment schedule and change orders).
Making it routine
- Ask for both prices on every large bid.
- Compute the break-even premium for your cost of cash.
- Pay on completed milestones, not on the calendar alone.
- Record the terms agreed and the discount earned.
Run your own numbers
Use the free holding cost calculator below to see what your cash costs per day on a project.