Write Down the City Inspector's Name and Number
The framing inspection is booked for Tuesday. The inspector’s office changes the slot and nobody can reach the person who knows. A note with the inspector’s name and the department’s booking line takes two minutes after the first visit. The question is how likely a booking mix-up is for the note to pay.
The steps
- Price the note: minutes × the value of your time.
- Price a booking mix-up: a missed slot, a wasted crew day and delay.
- Break-even chance = note cost ÷ mix-up cost.
- Plan the stages too (ask the city which inspections each permit needs and when).
A worked example
Example (illustrative arithmetic, not predictions)
The note takes 2 minutes at $60 an hour: $2. A booking mix-up costs $100. Every figure is a made-up round number.
| Chance of a booking mix-up | Expected cost avoided (chance × $100) | Avoided − $2 |
|---|---|---|
| 1% | $1 | −$1 |
| 2% | $2 | $0 (break-even) |
| 5% | $5 | +$3 |
| 10% | $10 | +$8 |
The note pays at a 2% chance of a booking mix-up: $2 ÷ $100. Across several inspections, it is plausible.
After the first visit, write the inspector’s name, the department’s booking line or email and the best time to call. Book through the department’s process and never ask for a shortcut.
Making it routine
- Write the inspector’s name after the first visit.
- Add the department’s booking line or email.
- Book through the department’s process.
- Never ask for a shortcut.
Run your own numbers
Use the free holding cost calculator below to see what a missed inspection slot costs on your own flip.