Ask Each Bidder to List What Is Excluded From the Bid
Two bids differ by $4,000. The cheaper one leaves out debris removal and paint. Nobody asked what was excluded. Asking each bidder for a short list takes three minutes. The question is how likely a hidden exclusion is for the step to pay.
The steps
- Price the step: minutes × the value of your time.
- Price a hidden exclusion: work you thought was in the price that is billed on top.
- Break-even chance = step cost ÷ exclusion cost.
- Compare bids fairly (send every bidder the same written scope).
A worked example
Example (illustrative arithmetic, not predictions)
The step takes 3 minutes at $60 an hour: $3. A hidden exclusion costs $600. Every figure is a made-up round number.
| Chance of a hidden exclusion | Expected cost avoided (chance × $600) | Avoided − $3 |
|---|---|---|
| 0.25% | $1.50 | −$1.50 |
| 0.5% | $3 | $0 (break-even) |
| 1.5% | $9 | +$6 |
| 3% | $18 | +$15 |
The step pays at a 0.5% chance of a hidden exclusion: $3 ÷ $600. With several bids, it is easily exceeded.
Ask each bidder to list exclusions, line them up side by side and price anything left out before comparing totals.
Making it routine
- Ask each bidder to list exclusions.
- Line them up side by side.
- Price anything left out before comparing totals.
- Put the final scope in the contract.