Write the Quote Date Next to Each Contractor Bid
The budget used a flooring bid from March, and the job starts in August at a higher price. The bid had no date on the budget line. Writing the quote date and how long it holds next to each bid takes six minutes. The question is how likely an expired quote is for the step to pay.
The steps
- Price the step: minutes × the value of your time.
- Price an expired quote: a higher price when work starts after the quote ran out.
- Break-even chance = step cost ÷ expired-quote cost.
- Pick the budget method too (rehab estimate per square foot vs line item).
A worked example
Example (illustrative arithmetic, not predictions)
The step takes 6 minutes at $60 an hour: $6. An expired quote costs $300 more. Every figure is a made-up round number.
| Chance of an expired quote | Expected cost avoided (chance × $300) | Avoided − $6 |
|---|---|---|
| 1% | $3 | −$3 |
| 2% | $6 | $0 (break-even) |
| 5% | $15 | +$9 |
| 8% | $24 | +$18 |
The step pays at a 2% chance of an expired quote: $6 ÷ $300. On a rehab that starts months after the bids, it is easily exceeded.
Write the date and the holding period next to each bid, flag the ones that expire before the start date and ask for a refreshed quote.
Making it routine
- Write the date and the holding period next to each bid.
- Flag bids that expire before the start date.
- Ask for a refreshed quote.
- Re-check the budget when the start date moves.
Run your own numbers
Use the free MAO calculator below to see how a higher rehab budget changes your maximum offer.