Flip Cash Cycle: How Many Days Until Your Cash Comes Back
Most flip analysis asks “how much will I make?” A second question matters as much: “how fast does the money come back?” Two projects with the same profit are not the same if one takes 120 days and the other 220.
The steps
- List the stages and the days each takes.
- Cash cycle = the total days.
- Cycles in a year = 365 ÷ cash cycle.
- Yearly profit from one slot of cash = profit per project × cycles in a year, if a similar deal is ready each time.
- Value of a day saved = monthly holding cost ÷ 30, plus the extra cycles the days make room for.
A worked example
Example (illustrative arithmetic, not a benchmark)
Profit per project $29,200 (sensitivity table) and holding cost $1,300 a month, $43.33 a day (holding costs). Every figure is a made-up round number.
| Stage | Baseline days | After changes |
|---|---|---|
| Purchase to rehab start (permits, crews) | 10 | 4 |
| Rehab | 90 | 90 |
| Listing prep (clean, photos) | 10 | 10 |
| Listing to contract | 35 | 30 |
| Contract to close | 30 | 30 |
| Cash cycle | 175 | 164 |
| Item | Baseline | After changes |
|---|---|---|
| Cycles in a year | 365 ÷ 175 = 2.086 | 365 ÷ 164 = 2.226 |
| Holding cost saved per project | 11 × $43.33 = $477 | |
| Profit per project | $29,200 | $29,677 |
| Yearly profit from one slot of cash | $60,903 | $66,049 |
Eleven days saved add $5,146 a year per slot of cash, 8.4% more. Saving ten days on the rehab alone gives 165 days and $65,553, which is $4,650 more. The figures assume a similar deal is ready after each sale, which is the weak link: with no deal ready, the saved days only save holding cost ($477).
Finding days to save
- Look at gaps between stages first, such as waiting for permits, materials or a crew (rehab schedule).
- Prepare the listing during the last weeks of rehab (staging and photos).
- Line up the next purchase before the current sale closes (deal sourcing funnel).
- Track actual days on every project and compare with the plan (weekly scorecard).