Rehab Schedule Basics: Find the Critical Path
A rehab has many tasks, but only a few of them decide when it ends. Finding those few shows an investor where a delay costs money and where it does not.
How to build the schedule
- List every task from the scope of work (how to write a scope of work).
- Estimate each task’s length in working days.
- Mark which tasks must finish before another can start.
- Run independent tasks side by side.
- Add up the longest chain. That chain is the critical path.
A worked example
Example (illustrative arithmetic, not market data)
Task lengths are made up for the example, in working days.
| Task | Days | Starts after |
|---|---|---|
| Demolition | 5 | start |
| Plumbing rough-in | 7 | demolition |
| Electrical rough-in | 10 | demolition |
| Rough-in inspection | 3 | plumbing and electrical |
| Drywall | 6 | inspection |
| Paint | 4 | drywall |
| Cabinets | 7 | drywall |
| Flooring | 5 | paint and cabinets |
| Punch list | 3 | flooring |
| Stage | Calculation | Days so far |
|---|---|---|
| Demolition | 5 | 5 |
| Rough-in (the longer of 7 and 10) | 5 + 10 | 15 |
| Inspection | 15 + 3 | 18 |
| Drywall | 18 + 6 | 24 |
| Paint and cabinets (the longer of 4 and 7) | 24 + 7 | 31 |
| Flooring | 31 + 5 | 36 |
| Punch list, finish | 36 + 3 | 39 |
The critical path runs through demolition, electrical, inspection, drywall, cabinets, flooring and the punch list: 39 working days, about eight weeks.
Which delays cost time
Assume holding costs of about $75 per working day, a rounded figure from the $1,560-a-month example (price cut or wait).
| Delay | New total | Days added | Cost at $75 a day |
|---|---|---|---|
| Electrical runs 4 days late | 43 days | 4 | $300 |
| Plumbing runs 4 days late (7 becomes 11) | 40 days | 1 | $75 |
| Paint runs 2 days late (4 becomes 6) | 39 days | 0 | $0 |
Electrical sits on the critical path, so each day it slips costs a day. Plumbing has 3 days of slack, so a 4-day slip costs only 1. Paint has 3 days of slack against cabinets, so 2 days of delay costs nothing. Spend your attention on electrical, inspections and cabinets (permits and inspections).
Use it
- Ask the contractor for a task schedule, not just a finish date.
- Check the critical path each week as tasks finish.
- Book inspections early, since they sit on the path.
- Tie payments to finished stages (contractor payments).
- Keep the schedule in the project file (flip project checklist).
Run your own numbers
Use the free holding cost calculator below to see what each extra week costs on your project.