Rehab Schedule Basics: Find the Critical Path

By DeskTech HQ · · 2 min read

A rehab has many tasks, but only a few of them decide when it ends. Finding those few shows an investor where a delay costs money and where it does not.

How to build the schedule

  1. List every task from the scope of work (how to write a scope of work).
  2. Estimate each task’s length in working days.
  3. Mark which tasks must finish before another can start.
  4. Run independent tasks side by side.
  5. Add up the longest chain. That chain is the critical path.

A worked example

Example (illustrative arithmetic, not market data)

Task lengths are made up for the example, in working days.

Task Days Starts after
Demolition 5 start
Plumbing rough-in 7 demolition
Electrical rough-in 10 demolition
Rough-in inspection 3 plumbing and electrical
Drywall 6 inspection
Paint 4 drywall
Cabinets 7 drywall
Flooring 5 paint and cabinets
Punch list 3 flooring
Stage Calculation Days so far
Demolition 5 5
Rough-in (the longer of 7 and 10) 5 + 10 15
Inspection 15 + 3 18
Drywall 18 + 6 24
Paint and cabinets (the longer of 4 and 7) 24 + 7 31
Flooring 31 + 5 36
Punch list, finish 36 + 3 39

The critical path runs through demolition, electrical, inspection, drywall, cabinets, flooring and the punch list: 39 working days, about eight weeks.

Which delays cost time

Assume holding costs of about $75 per working day, a rounded figure from the $1,560-a-month example (price cut or wait).

Delay New total Days added Cost at $75 a day
Electrical runs 4 days late 43 days 4 $300
Plumbing runs 4 days late (7 becomes 11) 40 days 1 $75
Paint runs 2 days late (4 becomes 6) 39 days 0 $0

Electrical sits on the critical path, so each day it slips costs a day. Plumbing has 3 days of slack, so a 4-day slip costs only 1. Paint has 3 days of slack against cabinets, so 2 days of delay costs nothing. Spend your attention on electrical, inspections and cabinets (permits and inspections).

Use it

  1. Ask the contractor for a task schedule, not just a finish date.
  2. Check the critical path each week as tasks finish.
  3. Book inspections early, since they sit on the path.
  4. Tie payments to finished stages (contractor payments).
  5. Keep the schedule in the project file (flip project checklist).

Run your own numbers

Use the free holding cost calculator below to see what each extra week costs on your project.

Quick answers

What is the critical path?

It is the longest chain of tasks that must happen one after another. The project cannot finish sooner than the critical path, and a delay to any task on it delays the finish.

What is the difference between a task on the critical path and one off it?

A task off the critical path has slack, which is spare time before it holds anything up. A task on the path has none, so every day it slips is a day added to the project.

How do you build a rehab schedule?

List the tasks, estimate each one's length, note which tasks must finish before others can start, and add up the longest chain. Tasks that can happen at the same time run in parallel.

Why does the critical path matter to an investor?

Every day on the critical path adds holding costs. Knowing which tasks control the finish tells you where to spend attention, and where a small delay does not matter.

Do the numbers in this guide apply to my project?

No. The task lengths and the $75-a-day holding cost are made-up round numbers for the example, not market data. Real schedules depend on the contractor, the permits and the property.

See DeskTech Deals →

Keep reading

Flip project management

Rush Fees: Paying to Finish a Rehab Faster

Learn how to compare a contractor rush fee with the holding costs saved by finishing sooner, and the days it must save to break even, with an example.

· 2 min read

This guide is general education, not legal, tax, or financial advice. Talk with a licensed professional about your situation.