Weekly Flip Scorecard: Budget, Schedule and Forecast
By the time a flip is obviously over budget, the money is gone. A short weekly check catches the drift in week nine instead of week sixteen, when changing course is still possible.
The weekly numbers
- Work done = budget × percent complete (weigh each part of the scope).
- Cost ratio = work done ÷ money spent.
- Work planned by now = budget × weeks used ÷ total weeks planned.
- Schedule ratio = work done ÷ work planned by now.
- Forecast final cost = budget ÷ cost ratio.
- Forecast total weeks = planned weeks ÷ schedule ratio.
A worked example
Example (illustrative arithmetic, not a benchmark)
A rehab budget of $70,000 with a contingency of $8,700 (contingency), planned for 16 weeks. At the end of week 9 the project is 45% complete and $38,500 has been spent. Every figure is a made-up round number.
| Measure | Calculation | Result |
|---|---|---|
| Work done | $70,000 × 45% | $31,500 |
| Money spent | $38,500 | |
| Over by | $38,500 − $31,500 | $7,000 |
| Cost ratio | $31,500 ÷ $38,500 | 0.82 |
| Work planned by week 9 | $70,000 × 9 ÷ 16 | $39,375 |
| Schedule ratio | $31,500 ÷ $39,375 | 0.80 |
| Forecast final cost | $70,000 ÷ 0.818 | $85,556 |
| Forecast over budget | $85,556 − $70,000 | $15,556 |
| After the $8,700 contingency | $15,556 − $8,700 | $6,856 uncovered |
| Forecast total weeks | 16 ÷ 0.80 | 20 weeks |
If nothing changes, the project ends about $15,556 over budget, $6,856 more than the contingency, and four weeks late. Four extra weeks also add holding cost (holding costs). The forecast is a warning, not a verdict.
What to do with it
- Find the cause: scope growth, price changes or slow work (overruns).
- Decide what to cut, delay or re-bid, and write down any change (change orders).
- Rerun the profit at the forecast cost and time (sensitivity table).
- Keep the weekly sheets to compare with the final result (year-end review).
Run your own numbers
Use the free holding cost calculator below to price the extra weeks the forecast shows.