Weekly Flip Scorecard: Budget, Schedule and Forecast

By DeskTech HQ · · 2 min read

By the time a flip is obviously over budget, the money is gone. A short weekly check catches the drift in week nine instead of week sixteen, when changing course is still possible.

The weekly numbers

  1. Work done = budget × percent complete (weigh each part of the scope).
  2. Cost ratio = work done ÷ money spent.
  3. Work planned by now = budget × weeks used ÷ total weeks planned.
  4. Schedule ratio = work done ÷ work planned by now.
  5. Forecast final cost = budget ÷ cost ratio.
  6. Forecast total weeks = planned weeks ÷ schedule ratio.

A worked example

Example (illustrative arithmetic, not a benchmark)

A rehab budget of $70,000 with a contingency of $8,700 (contingency), planned for 16 weeks. At the end of week 9 the project is 45% complete and $38,500 has been spent. Every figure is a made-up round number.

Measure Calculation Result
Work done $70,000 × 45% $31,500
Money spent $38,500
Over by $38,500 − $31,500 $7,000
Cost ratio $31,500 ÷ $38,500 0.82
Work planned by week 9 $70,000 × 9 ÷ 16 $39,375
Schedule ratio $31,500 ÷ $39,375 0.80
Forecast final cost $70,000 ÷ 0.818 $85,556
Forecast over budget $85,556 − $70,000 $15,556
After the $8,700 contingency $15,556 − $8,700 $6,856 uncovered
Forecast total weeks 16 ÷ 0.80 20 weeks

If nothing changes, the project ends about $15,556 over budget, $6,856 more than the contingency, and four weeks late. Four extra weeks also add holding cost (holding costs). The forecast is a warning, not a verdict.

What to do with it

  1. Find the cause: scope growth, price changes or slow work (overruns).
  2. Decide what to cut, delay or re-bid, and write down any change (change orders).
  3. Rerun the profit at the forecast cost and time (sensitivity table).
  4. Keep the weekly sheets to compare with the final result (year-end review).

Run your own numbers

Use the free holding cost calculator below to price the extra weeks the forecast shows.

Quick answers

What is a flip scorecard?

It is a one-page weekly check of three things: how much of the work is done, how much money has been spent, and how many weeks have passed. Comparing them shows whether the project is on track and forecasts where it will end up.

How do I measure percent complete?

Weigh each part of the scope by its budget, mark each part's progress, and add them up. A draw inspection or walkthrough is a good time to do it.

What do the ratios mean?

Cost ratio is the value of the work done divided by the money spent. Schedule ratio is the work done divided by the work planned by now. Below 1.0 means over budget or behind.

Is the forecast reliable?

It assumes the rest of the project will go as the first part did. That is a simple rule, not a promise. Recheck it weekly and replace it with a better estimate when you have one.

Do the numbers in this guide apply to my project?

No. The budget, progress and weeks are made up for the example. They are not benchmarks or a prediction of results.

Keep reading

Flip project management

Budget Check Frequency: Weekly or Monthly?

Learn how to compare the extra time a weekly rehab budget check takes with the overrun it can catch weeks sooner, and the odds that make weekly worthwhile.

· 2 min read

This guide is general education, not legal, tax, or financial advice. Talk with a licensed professional about your situation.