Flip Cash Timeline: Month by Month and Peak Cash Needed
“The deal makes $29,200” is not the same as “I need $29,200.” You need about $247,000 in hand for six months before the profit shows up. A month-by-month timeline shows how much, and when.
The steps
- List every cash out by month: purchase, buying costs, rehab draws, holding costs.
- Add the cash in: the net sale price in the sale month.
- Keep a running total. The lowest point is the peak cash needed.
- Repeat with a loan: your own cash plus interest, and the loan paid off at sale.
- Return on your own cash = profit ÷ peak cash.
A worked example
Example (illustrative arithmetic, not market data)
Purchase $180,000, buying costs $4,000, rehab $55,000 spent evenly in months 1 to 3, holding cost $1,300 a month for 6 months, sale for $300,000 with 8% selling costs at the end of month 6. Every figure is a made-up round number (holding costs).
All cash (running total of cash out)
| Month | Cash out | Running total |
|---|---|---|
| 0 | $184,000 | −$184,000 |
| 1 | $19,633 | −$203,633 |
| 2 | $19,633 | −$223,267 |
| 3 | $19,633 | −$242,900 |
| 4 | $1,300 | −$244,200 |
| 5 | $1,300 | −$245,500 |
| 6 | $1,300 | −$246,800 |
| Sale | +$276,000 | +$29,200 |
Peak cash is $246,800, and the return on it is $29,200 ÷ $246,800 = 11.8% in 6 months.
With a loan. Borrow 80% of the purchase ($144,000) and the whole rehab as draws ($55,000), at 11% interest-only, with no points or fees in this example. Interest is charged each month on the balance at the start of the month.
| Item | Amount |
|---|---|
| Your own cash at the start (20% of purchase + buying costs) | $40,000 |
| Interest over 6 months | $9,937 |
| Holding costs (6 × $1,300) | $7,800 |
| Your peak cash (month 6, before the sale) | $57,737 |
| Profit after interest | $29,200 − $9,937 = $19,263 |
| Return on your own cash | $19,263 ÷ $57,737 = 33.4% |
The loan cuts the cash you need by $189,063 and cuts profit by $9,937, but raises the return on your own cash from 11.8% to 33.4%. Points, fees and a longer schedule would reduce that return (cash, hard money or partner).
Using the timeline
- Add a reserve on top of peak cash (cash reserve).
- Rerun it with two more months of delay (sensitivity table).
- Compare it with what your funds can support at once (flip goals).
- Update the timeline each week against actual spending (weekly scorecard).