Why Did This Flip Make Less? A Profit Variance Breakdown
A flip planned to make $29,200 and made $2,080. “It didn’t go well” is true and useless. A variance breakdown says where the $27,120 went, in an order you can act on.
The steps
- Compute planned profit and actual profit with the same formula (sensitivity table).
- Price variance = (actual sale price − planned sale price) × (1 − selling cost %).
- Rehab variance = planned rehab − actual rehab.
- Time variance = (planned months − actual months) × monthly holding cost.
- Add any other differences, such as buying costs, and check that the pieces sum to the total.
A worked example
Example (illustrative arithmetic, not market data)
Purchase $180,000, buying costs $4,000, selling costs 8% and holding cost $1,300 a month in both. Every figure is a made-up round number.
| Item | Planned | Actual |
|---|---|---|
| Sale price | $300,000 | $284,000 |
| Rehab | $55,000 | $63,500 |
| Months held | 6 | 9 |
| Profit | $29,200 | $2,080 |
| Cause | Calculation | Variance | Share of the miss |
|---|---|---|---|
| Sale price | ($284,000 − $300,000) × 0.92 | −$14,720 | 54.3% |
| Rehab cost | $55,000 − $63,500 | −$8,500 | 31.3% |
| Time | (6 − 9) × $1,300 | −$3,900 | 14.4% |
| Total | −$27,120 | 100% |
The pieces sum to the total ($14,720 + $8,500 + $3,900 = $27,120). The sale price explains over half of the miss, so the first fix is the value estimate (comps). Rehab is next (rehab estimates). Part of the delay may have come from the overrun, so the time and rehab pieces overlap.
What to do with it
- Write one sentence for each cause: what happened and what you will change.
- Test the next deal at the lower price and higher cost that this one showed (break-even price).
- Add the result to a running list across projects (year-end review).
- Reset your contingency and schedule assumptions from the real numbers (contingency).
Run your own numbers
Use the free holding cost calculator below to price the months you actually held.