Why Did This Flip Make Less? A Profit Variance Breakdown

By DeskTech HQ · · 2 min read

A flip planned to make $29,200 and made $2,080. “It didn’t go well” is true and useless. A variance breakdown says where the $27,120 went, in an order you can act on.

The steps

  1. Compute planned profit and actual profit with the same formula (sensitivity table).
  2. Price variance = (actual sale price − planned sale price) × (1 − selling cost %).
  3. Rehab variance = planned rehab − actual rehab.
  4. Time variance = (planned months − actual months) × monthly holding cost.
  5. Add any other differences, such as buying costs, and check that the pieces sum to the total.

A worked example

Example (illustrative arithmetic, not market data)

Purchase $180,000, buying costs $4,000, selling costs 8% and holding cost $1,300 a month in both. Every figure is a made-up round number.

Item Planned Actual
Sale price $300,000 $284,000
Rehab $55,000 $63,500
Months held 6 9
Profit $29,200 $2,080
Cause Calculation Variance Share of the miss
Sale price ($284,000 − $300,000) × 0.92 −$14,720 54.3%
Rehab cost $55,000 − $63,500 −$8,500 31.3%
Time (6 − 9) × $1,300 −$3,900 14.4%
Total −$27,120 100%

The pieces sum to the total ($14,720 + $8,500 + $3,900 = $27,120). The sale price explains over half of the miss, so the first fix is the value estimate (comps). Rehab is next (rehab estimates). Part of the delay may have come from the overrun, so the time and rehab pieces overlap.

What to do with it

  1. Write one sentence for each cause: what happened and what you will change.
  2. Test the next deal at the lower price and higher cost that this one showed (break-even price).
  3. Add the result to a running list across projects (year-end review).
  4. Reset your contingency and schedule assumptions from the real numbers (contingency).

Run your own numbers

Use the free holding cost calculator below to price the months you actually held.

Quick answers

What is a profit variance?

It is the difference between the profit you planned and the profit you got. Splitting it into causes, such as sale price, rehab cost and time, shows which part of the plan was wrong.

Why split it up?

A total miss does not say what to change. If most of the gap came from the sale price, the fix is better comps. If it came from rehab cost, the fix is a better scope and bids.

When should I do this?

Soon after each sale, while the numbers and the reasons are fresh. Keep the results in one place so patterns show across projects.

What if the causes overlap?

They can. A rehab overrun often causes delay, for example. Choose a clear order, note any overlap, and use the breakdown as a guide rather than an exact accounting.

Do the numbers in this guide apply to my project?

No. The prices, costs and months are made up for the example. They are not benchmarks or a prediction of results.