A rehab budget with no buffer is a budget that will be wrong. The usual fix is a flat 10%. A better fix is to ask which parts of the job are most likely to surprise you, and size the buffer to match.
The steps
Split the rehab budget into groups of work.
Give each group a risk level and a percentage.
Contingency = group cost × percentage, added up across groups.
Subtract the contingency from planned profit and see if the deal still works (break-even price).
A worked example
Example (illustrative arithmetic, not a standard)
A $70,000 rehab budget (rehab budget). Every figure is a made-up round number.
Work group
Budget
Risk
Percentage
Contingency
Cosmetic (paint, floors)
$18,000
Low
5%
$900
Kitchen and baths
$24,000
Medium
10%
$2,400
Mechanical (HVAC, electrical, plumbing)
$16,000
Medium-high
15%
$2,400
Structure and unknowns
$12,000
High
25%
$3,000
Total
$70,000
12.43%
$8,700
A flat 10% would set aside $7,000, $1,700 less. The risk-based buffer puts the extra where the surprises are likelier. The budget with contingency is $78,700. If the plan showed $30,000 of profit before any contingency, it shows $21,300 after it. If the deal only works at $30,000, the deal is thinner than it looked.
Using the contingency
Spend it only on real surprises, and log each one (overruns).
Price changes through written change orders (change orders).
Keep a separate cash reserve outside the budget (cash reserve).
After the project, compare what was used with what was set aside and adjust the percentages (year-end review).
Run your own numbers
Use the free holding cost calculator below to see how a longer project adds to the cost beside the rehab budget.
Quick answers
What is a rehab contingency?
It is money set aside inside the rehab budget for costs that are likely but not yet known, such as hidden damage or price changes. It is planned in advance, separate from a cash reserve.
Why not use one flat percentage?
A flat percentage treats a paint job and a foundation repair the same. Sizing by risk puts more buffer where surprises are more likely and less where the work is simple.
How do I pick the percentages?
Start with your own past projects: compare planned and actual cost for each type of work. If you have no history, choose cautious numbers and adjust after each project.
How is contingency different from a cash reserve?
Contingency is part of the rehab budget for expected surprises. A reserve is extra cash outside the budget for events such as a delayed sale. Both are worth planning for.
Do the numbers in this guide apply to my project?
No. The line items, risk levels and percentages are made up for the example. They are not market data, a standard or a prediction of results.
Run your own numbers
The Holding Cost Calculator is free and works in your browser. You can email yourself the report afterwards.