Floor Protection on a Rehab: The Damage Odds That Pay
New floors are often installed before the painters, plumbers and cleaners are finished. Every trade that walks over them can scratch or stain them. Protective covering costs little. The question is how likely damage has to be to justify it.
The steps
- Get the cost of covering the floors.
- Estimate the cost to repair damage, including the days it adds.
- Break-even chance = protection cost ÷ repair cost.
- Compare with how many trades still have work to do (mid-project cleanups vs one final clean).
A worked example
Example (illustrative arithmetic, not predictions)
Protection costs $300. Repairing damaged floors costs $2,500. Every figure is a made-up round number.
| Chance of floor damage without protection | Expected cost avoided (chance × $2,500) | Avoided − $300 |
|---|---|---|
| 5% | $125 | −$175 |
| 12% | $300 | $0 (break-even) |
| 25% | $625 | +$325 |
Protection pays at a 12% chance of damage: $300 ÷ $2,500. With several trades still working after the floors go in, the chance is well above that. With one painter and a light touch-up, it is lower.
Ask whether the order of work can avoid the issue: floors last when possible. If not, cover them, and write into each contract who repairs what (debris and site costs).
Making it routine
- Plan the order of trades.
- Cover floors as soon as they are down.
- Compute the break-even chance.
- Write damage responsibility into contracts.
Run your own numbers
Use the free holding cost calculator below to see what a repair delay costs each day.