Daily Site Log: The Dispute Odds That Pay
Disputes with contractors usually turn on who said what and when. A short daily note on a rehab costs minutes. The question is how likely a dispute has to be for the notes to pay for themselves.
The steps
- Cost the log: minutes a day × days × your hourly value.
- Estimate the cost of a dispute.
- Break-even chance = log cost ÷ dispute cost.
- Keep photos and messages alongside the log (as-built photos before the walls close).
A worked example
Example (illustrative arithmetic, not predictions)
Ten minutes a day for 60 days is 10 hours, $400 at $40. A dispute could cost $8,000. Every figure is a made-up round number.
| Chance of a dispute on the project | Expected cost avoided (chance × $8,000) | Avoided − $400 |
|---|---|---|
| 2% | $160 | −$240 |
| 5% | $400 | $0 (break-even) |
| 10% | $800 | +$400 |
The log pays at a 5% chance of a dispute: $400 ÷ $8,000. On a rehab with several trades, change orders and a tight schedule, disputes are more common than that.
A log does not need to be long. Date, who was there, what was done, what was delivered, what was agreed. Write it that day. A note written weeks later is worth little. And remember that the contract may require written notice of problems within a number of days, which a log alone does not satisfy (comparing contractor bids).
Making it routine
- Start the log on day one.
- Write it the same day, every working day.
- Compute the break-even chance.
- Send contract-required notices in the form the contract says.