Contractor Deposit: 10% or a Third? The Risk That Decides
A contractor may offer a small discount for a larger deposit. It sounds like a good deal until the contractor stops showing up. The question is how likely that has to be to cancel the discount.
The steps
- Compare the small deposit with the large one.
- Extra at risk = large deposit − small deposit.
- Break-even chance = discount ÷ extra at risk.
- Judge how likely this contractor is to fail you (comparing contractor bids).
A worked example
Example (illustrative arithmetic, not typical figures)
The bid is $40,000. A 10% deposit is $4,000. A 33% deposit is $13,200 and earns a 2% discount, $800. The extra at risk is $9,200. Every figure is a made-up round number.
| Chance the contractor abandons the job | Expected loss on the extra deposit (chance × $9,200) | Discount − expected loss |
|---|---|---|
| 3% | $276 | +$524 |
| 8.7% | $800 | $0 (break-even) |
| 15% | $1,380 | −$580 |
The larger deposit is a bad trade if there is more than about a 9% chance of the contractor not finishing: $800 ÷ $9,200. For a known contractor you have used many times, it may be well below that. For a new one, it may not be.
Whatever the odds, the better route is to pay against progress and use the draw schedule. A contractor paid for work done has little to lose by finishing (net-7 vs net-30 pay terms).
Making it routine
- Check licensing and liens.
- Ask for references on similar jobs.
- Compute the break-even chance.
- Prefer payment against progress.
Run your own numbers
Use the free holding cost calculator below to see what a stalled job costs each day.