Paid Scope of Work Before an Offer: The 3% Test
An offer depends on the repair estimate. A rough estimate made on a walkthrough can miss things. A written scope costs a little. The question is how likely an underestimate has to be to justify the fee.
The steps
- Get the fee for a written scope.
- Estimate how much your own estimate might be low.
- Break-even chance = fee ÷ underestimate.
- Compare with the property’s condition and your experience (writing a rehab scope of work).
A worked example
Example (illustrative arithmetic, not predictions)
The scope costs $150. A missed item would add $4,500 to the repairs. Every figure is a made-up round number.
| Chance your estimate is low by $4,500 | Expected loss avoided (chance × $4,500) | Avoided − $150 |
|---|---|---|
| 2% | $90 | −$60 |
| 3.3% | $150 | $0 (break-even) |
| 5% | $225 | +$75 |
| 10% | $450 | +$300 |
The scope pays at about a 3% chance of a miss: $150 ÷ $4,500. For a house you know well, with a small scope, it may not. For a large rehab or an unfamiliar system, the odds are much higher.
A higher estimate lowers the price you can pay, and a lower price is the real saving (rehab estimates per square foot vs line item).
Making it routine
- Do your own walkthrough list first.
- Order a scope when the project is large or unfamiliar.
- Compute the break-even chance.
- Update your maximum offer with the result.
Run your own numbers
Use the free MAO calculator below to see how a higher repair estimate lowers the maximum you should offer.