Percent Complete by Trade in Writing: The Odds That Pay
A draw request says the job is 60 percent done. Is plumbing 90 percent and drywall 20? A trade-by-trade breakdown in writing shows where the work stands. Reading it takes ten minutes. The question is how likely an overstatement is for the review to pay.
The steps
- Price the review: minutes × the value of your time.
- Estimate the amount overpaid if a trade is overstated.
- Break-even chance = review cost ÷ overpayment.
- Check it against the inspection (draw inspections: cost vs overpayment saved).
A worked example
Example (illustrative arithmetic, not predictions)
The review takes 10 minutes at $60 an hour: $10. An overstated trade would mean paying $500 ahead of the work. Every figure is a made-up round number.
| Chance a trade is overstated | Expected overpayment avoided (chance × $500) | Avoided − $10 |
|---|---|---|
| 1% | $5 | −$5 |
| 2% | $10 | $0 (break-even) |
| 5% | $25 | +$15 |
| 10% | $50 | +$40 |
The review pays at a 2% chance of an overstated trade: $10 ÷ $500. Contractors who bill by the job rather than by the trade overstate early work more often than that.
Ask for a short table: each trade, its contract amount, the percent complete and the amount requested. Compare it with the inspector’s findings, and ask about any trade where the two differ.
Making it routine
- Ask for percent complete by trade.
- Compare it with the inspector’s findings.
- Ask about differences before paying.
- Keep the table with the draw record.