Percent Complete by Trade in Writing: The Odds That Pay

By DeskTech HQ · · 1 min read

A draw request says the job is 60 percent done. Is plumbing 90 percent and drywall 20? A trade-by-trade breakdown in writing shows where the work stands. Reading it takes ten minutes. The question is how likely an overstatement is for the review to pay.

The steps

  1. Price the review: minutes × the value of your time.
  2. Estimate the amount overpaid if a trade is overstated.
  3. Break-even chance = review cost ÷ overpayment.
  4. Check it against the inspection (draw inspections: cost vs overpayment saved).

A worked example

Example (illustrative arithmetic, not predictions)

The review takes 10 minutes at $60 an hour: $10. An overstated trade would mean paying $500 ahead of the work. Every figure is a made-up round number.

Chance a trade is overstated Expected overpayment avoided (chance × $500) Avoided − $10
1% $5 −$5
2% $10 $0 (break-even)
5% $25 +$15
10% $50 +$40

The review pays at a 2% chance of an overstated trade: $10 ÷ $500. Contractors who bill by the job rather than by the trade overstate early work more often than that.

Ask for a short table: each trade, its contract amount, the percent complete and the amount requested. Compare it with the inspector’s findings, and ask about any trade where the two differ.

Making it routine

  1. Ask for percent complete by trade.
  2. Compare it with the inspector’s findings.
  3. Ask about differences before paying.
  4. Keep the table with the draw record.

Run your own numbers

Use the free fix-and-flip loan sizer below to see how an overpaid draw changes the funds left on a rehab.

Quick answers

What does the breakdown show?

How far along each trade is, such as plumbing, electrical and drywall.

How do I price the review?

The minutes times the value of your time.

What does overstatement cost?

Paying ahead of the work.

What is the break-even chance?

The review's cost divided by the amount overpaid.

Do the numbers in this guide apply to my draws?

No. The time, cost and odds are made up for the example. They are not predictions.

Keep reading

Draw management

Material Receipts With Each Draw: The Odds

Learn how to price a five-minute check of material receipts attached to a draw request and find the overbilling chance that makes it pay.

· 1 min read
Draw management

Number Each Contractor Draw Invoice in Sequence

Learn how to price asking the contractor to number each draw invoice in sequence and find the duplicate-invoice chance at which two minutes pays.

· 1 min read

This guide is general education, not legal, tax, or financial advice. Talk with a licensed professional about your situation.