Draw Inspections: What Checking Each Draw Costs vs Saves
Inspections cost money and time. So does paying for work that was not done. The question is not whether to check draws, but how much checking each draw deserves.
The steps
- Total the draws on the loan and the cost of each kind of check: inspection, photo review, lien waiver (site visit report).
- Estimate the share of draw money that is overpaid or paid early under each kind of check, from your own history.
- Multiply by the draw total to get the expected overpayment.
- Add the checking cost to get the total cost of each approach.
- Compare, and find the error rate at which the cheaper check stops being cheaper.
A worked example
Example (illustrative arithmetic, not market data)
A $60,000 rehab holdback paid in 4 draws. A third-party inspection costs $150 and the lender’s review time costs $120, so $270 a draw. A photo-only review costs $60 of the lender’s time. Assumed overpayment: 0.5% of draw money when inspected and 2% with photos only. The lender charges a $250 draw fee. Every figure is a made-up round number.
| Approach | Checking cost | Expected overpayment | Total |
|---|---|---|---|
| Inspect all 4 draws (4 × $270) | $1,080 | 0.5% × $60,000 = $300 | $1,380 |
| Photos only (4 × $60) | $240 | 2% × $60,000 = $1,200 | $1,440 |
| Inspect 2 draws, photos on 2 | $660 | $150 + $600 = $750 | $1,410 |
The fee brings in $1,000 against $1,080 of inspection cost, so inspecting every draw costs the lender $80 net. The three approaches are within $60 of each other, which means the answer turns on the error rate. Photos alone are cheaper only if their overpayment rate is below 1.9% ($1,380 − $240 = $1,140, divided by $60,000). At 4% the photo-only total is $240 + $2,400 = $2,640 against $1,380 for inspections (draw review checklist).
The exact error rates here are guesses, which is the point: until you have your own numbers, a hybrid is a reasonable start, such as inspecting the first, the largest and the last draw and using photos and lien waivers in between (lien waivers). Savings on a loan this size are small. The risk is in the unusual draw, so keep the right to inspect any draw.
Making it routine
- Write down which draws get an inspection, and which get photos and waivers.
- Record requested versus approved amounts on every draw.
- Review your error rate after ten or so loans and adjust.
- Put the draw fee and the lender’s right to inspect in the loan documents (draw schedule).
Run your own numbers
Use the free fix-and-flip loan sizer below to see the holdback on a loan before you plan its draws.