Rehab Budget Review: Is the Holdback Big Enough?
On a rehab loan, the holdback is a promise to finish the work. That promise is only as good as the budget behind it. A quick review before funding can catch a budget that is short before it becomes a stalled project.
What to compare
- The borrower’s budget.
- A written contractor bid and the scope of work (how to write a scope of work).
- A contingency for the unknown (rehab estimates).
- The holdback in the loan terms (interest reserves).
- The value the project is expected to add.
A worked example
Example (illustrative arithmetic, not market data)
Assume a $120,000 purchase, an expected finished value of $225,000, a borrower budget of $40,000 and a holdback request of $40,000. The contractor’s written bid is $42,400, and the lender adds a 10% contingency (an assumption). Every figure is a made-up round number.
| Check | Calculation | Amount |
|---|---|---|
| Contractor bid | given | $42,400 |
| Contingency, 10% | 10% × $42,400 | $4,240 |
| Budget needed | $42,400 + $4,240 | $46,640 |
| Holdback requested | given | $40,000 |
| Shortfall | $46,640 − $40,000 | $6,640 |
| Value gain | $225,000 − $120,000 | $105,000 |
| Gain per dollar of rehab | $105,000 ÷ $46,640 | 2.25 |
| Rehab as a share of value | $46,640 ÷ $225,000 | 20.7% |
The holdback leaves a $6,640 gap against the bid plus contingency. The value gain is 2.25 times the rehab cost, so the project still looks sound if the gap is filled. The lender might require the borrower to put in the $6,640 from their own cash, reduce the scope or reduce the loan.
What to do with a gap
- Ask for the gap to be funded in cash before the first draw.
- Hold that cash in a separate account or have it spent first.
- Document the decision in the loan file (a pre-funding checklist).
- Review the budget again at each draw (reviewing a draw request).