Comparing Contractor Bids: Scope, Exclusions and Time

By DeskTech HQ · · 1 min read

Three bids for the same house can be $12,000 apart and still not describe the same job. Putting them on a like-for-like basis takes three steps: match the scope, add back what each leaves out, and price the time.

The steps

  1. Give every contractor the same written scope (walkthrough checklist).
  2. List what each bid excludes and put a price on it.
  3. Adjusted cost = bid + excluded items + (weeks × weekly holding cost).
  4. Check references, license and insurance before you choose.

A worked example

Example (illustrative arithmetic, not market data)

Weekly holding cost is $1,150 (holding costs). Every figure is a made-up round number.

Bid Price Excluded items Weeks Cost of weeks Adjusted cost
A $62,000 $6,500 (permits, dumpster) 14 $16,100 $84,600
B $71,500 $0 (all included) 11 $12,650 $84,150
C $58,000 $13,000 (allowances, permits) 16 $18,400 $89,400

Bid C is $13,500 below bid B on the page and $5,250 above it once exclusions and time are counted. Bids A and B are $450 apart, so the choice comes down to risk, references and payment terms. Add the same contingency to each bid before comparing (overruns).

Before you sign

  1. Make sure the contract names the scope, the price, the schedule and how changes are priced (scope changes).
  2. Tie payments to finished work, not to dates (rehab schedule).
  3. Keep a reserve for what the bid does not cover (cash reserve).

Run your own numbers

Use the free holding cost calculator below to price your own weekly cost and see what each extra week adds.

Quick answers

Why is the lowest bid not always the cheapest?

Bids often leave different things out, such as permits, dumpsters, finish allowances or cleanup. Adding those back, and counting what extra weeks cost in holding costs, can change which bid is lowest.

What should every bid include to be comparable?

The same written scope, a list of what is excluded, who pulls permits, how payment is scheduled, and an estimated start and finish. If a bid is missing one of these, ask before comparing.

How do I price the time difference?

Multiply the extra weeks by your weekly holding cost: interest, taxes, insurance and utilities. A bid that finishes three weeks earlier may save more than it costs.

Should I include a contingency?

Most projects plan one, since scope changes and surprises are common. Apply the same percentage to every bid so the comparison stays fair.

Do the numbers in this guide apply to my project?

No. The bids, exclusions and weekly cost are made up for the example. They are not market data or a prediction of results.

Keep reading

Flip project management

Drying Time Before Flooring: Wait or Rush?

Learn how to weigh the holding cost of waiting for a subfloor to dry against the chance of flooring failure if you rush, and the odds that favor waiting.

· 2 min read
Flip project management

Overlapping Trades: Days Saved vs Rework Risk

Learn how to weigh the days saved by letting two trades work at once against the chance that one damages the other's work, and the odds that favor it.

· 2 min read

This guide is general education, not legal, tax, or financial advice. Talk with a licensed professional about your situation.