Three bids for the same house can be $12,000 apart and still not describe the same job. Putting them on a like-for-like basis takes three steps: match the scope, add back what each leaves out, and price the time.
Check references, license and insurance before you choose.
A worked example
Example (illustrative arithmetic, not market data)
Weekly holding cost is $1,150 (holding costs). Every figure is a made-up round number.
Bid
Price
Excluded items
Weeks
Cost of weeks
Adjusted cost
A
$62,000
$6,500 (permits, dumpster)
14
$16,100
$84,600
B
$71,500
$0 (all included)
11
$12,650
$84,150
C
$58,000
$13,000 (allowances, permits)
16
$18,400
$89,400
Bid C is $13,500 below bid B on the page and $5,250 above it once exclusions and time are counted. Bids A and B are $450 apart, so the choice comes down to risk, references and payment terms. Add the same contingency to each bid before comparing (overruns).
Before you sign
Make sure the contract names the scope, the price, the schedule and how changes are priced (scope changes).
Tie payments to finished work, not to dates (rehab schedule).
Keep a reserve for what the bid does not cover (cash reserve).
Run your own numbers
Use the free holding cost calculator below to price your own weekly cost and see what each extra week adds.
Quick answers
Why is the lowest bid not always the cheapest?
Bids often leave different things out, such as permits, dumpsters, finish allowances or cleanup. Adding those back, and counting what extra weeks cost in holding costs, can change which bid is lowest.
What should every bid include to be comparable?
The same written scope, a list of what is excluded, who pulls permits, how payment is scheduled, and an estimated start and finish. If a bid is missing one of these, ask before comparing.
How do I price the time difference?
Multiply the extra weeks by your weekly holding cost: interest, taxes, insurance and utilities. A bid that finishes three weeks earlier may save more than it costs.
Should I include a contingency?
Most projects plan one, since scope changes and surprises are common. Apply the same percentage to every bid so the comparison stays fair.
Do the numbers in this guide apply to my project?
No. The bids, exclusions and weekly cost are made up for the example. They are not market data or a prediction of results.
Run your own numbers
The Holding Cost Calculator is free and works in your browser. You can email yourself the report afterwards.
Learn how a flipper can prepare complete draw packages so funds arrive on time, what each delay costs in holding cost, and when a cash float is worth it.
Learn how to weigh the holding cost of waiting for a subfloor to dry against the chance of flooring failure if you rush, and the odds that favor waiting.