Skip the Paperwork on Small Draws? The Size That Pays
A full review on every draw protects the lender, but a draw for a few hundred dollars may cost more to review than it puts at risk. The question is where the line sits.
The steps
- Total the cost of a full review: staff time, photos and any inspection.
- Estimate the share of a draw that is overpaid when you do not check.
- Break-even draw size = review cost ÷ overpayment rate.
- Set a lighter review below that size (lien waivers on draws).
A worked example
Example (illustrative arithmetic, not benchmarks)
A full review costs $45. Without it, 1.5% of a draw tends to be overpaid. Every figure is a made-up round number.
| Draw size | Expected overpayment (1.5%) | Overpayment − $45 review |
|---|---|---|
| $1,500 | $22.50 | −$22.50 |
| $3,000 | $45.00 | $0 (break-even) |
| $6,000 | $90.00 | +$45.00 |
Below $3,000, the full review costs more than the risk: $45 ÷ 0.015. Above it, review pays. A $1,500 draw can get a photo and an invoice. A $6,000 draw gets the full package.
The threshold should be conservative. Small draws repeated many times add up, and some problems, such as a lien claim, do not scale with the size of one draw. Keep lien waivers wherever the documents or law call for them (the minimum draw size).
Making it routine
- Set a review threshold in the loan policy.
- Track overpayments by draw size.
- Compute the break-even size.
- Keep the lighter review documented.
Run your own numbers
Use the free fix-and-flip loan sizer below to see how the draw schedule fits the loan.