Lien Waivers and Draws: What a Lender Should Collect
A borrower asks for a draw to pay the contractor. The contractor is paid. The contractor then does not pay a subcontractor, and the subcontractor files a claim against the property. Lien waivers are how a lender tries to stop that chain.
What to collect
- A waiver from the general contractor with each draw, for the work paid so far.
- Waivers from subcontractors and suppliers above a dollar amount set in your policy.
- A final waiver from each at the end of the project.
- A list of who worked on the property, so missing names stand out (draw checklist).
- A title update or lien search before large draws and at the end (title commitment).
A worked example
Example (illustrative arithmetic, not legal advice)
The loan from the downside test: $165,750 owed in a bad case, 8% selling costs, expected value $240,000 (downside test). A subcontractor was never paid and files a claim. Assume, for the example only, that the claim is paid ahead of the lender; in some states it may not be. Every figure is a made-up round number.
| Sale price | Net after 8% | Cushion, no claim | After a $9,000 claim | After a $12,000 claim |
|---|---|---|---|---|
| $216,000 (−10%) | $198,720 | $32,970 | $23,970 | $20,970 |
| $192,000 (−20%) | $176,640 | $10,890 | $1,890 | −$1,110 |
| $168,000 (−30%) | $154,560 | −$11,190 | −$20,190 | −$23,190 |
At the −20% price, a $9,000 claim removes most of the cushion and a $12,000 claim turns it into a loss. A waiver is cheap by comparison: it costs the contractor a signature, and costs the lender a minute of checking.
Making it routine
- Put the waiver rule in the policy and the loan agreement (policy manual).
- Release a draw only when the waivers match the work and the people (draw schedule).
- Keep the waivers in the loan file (loan file checklist).
- Use state-specific forms from an attorney or title company.
Run your own numbers
Use the free fix-and-flip loan sizer below to size the loan before you plan the draws.