Minimum Draw Size: Fewer Draws or Friendlier Terms?
A borrower with a $60,000 holdback could ask for $3,000 draws or $10,000 draws. The lender’s cost per draw is the same either way, so many small draws cost the lender much more. A minimum draw size trades that cost against what it asks of the borrower.
The steps
- Price a draw: inspection, review time and the wire (draw inspections).
- Count the draws under a small request size and under a minimum.
- Multiply by the cost per draw to get the lender’s saving.
- Estimate the borrower’s extra float: the cash it must fund before each draw, and its cost.
- Compare the two, and set a minimum that is low enough to be workable (draw fees).
A worked example
Example (illustrative arithmetic, not benchmarks)
A $60,000 holdback. Each draw costs the lender $225. Under $3,000 requests there would be 20 draws. Under a $10,000 minimum there would be 6. With the minimum, the borrower funds on average $5,000 more of the work from its own cash, for about 20 days per draw, and its cash costs 12% a year. Every figure is a made-up round number.
| Item | 20 small draws | 6 draws with a $10,000 minimum |
|---|---|---|
| Draws | 20 | 6 |
| Lender’s cost (× $225) | $4,500 | $1,350 |
| Lender’s saving | $3,150 | |
| Borrower’s extra float cost ($5,000 × 12% ÷ 365 × 20 days = $32.88 a draw, × 6) | $197 |
The lender saves $3,150 and the borrower pays about $197 more in carrying cost. On these numbers a minimum is a good trade for the lender and a small one for the borrower. The borrower’s real cost can be higher if its cash is scarce, because it may have to delay work or find short-term money. A minimum set too high can stall projects, which hurts both sides (draw turnaround).
Many lenders pair a minimum with a final-draw exception, so the last small amount of the holdback can be released without needing to reach the minimum (final draw holdback).
Making it routine
- Track the cost of each draw and the number of draws per loan.
- Set a minimum from the numbers, not from habit.
- Write the minimum and the final-draw exception into the loan documents.
- Review borrower feedback and stalled projects each quarter.
Run your own numbers
Use the free fix-and-flip loan sizer below to see how the holdback divides across draws.