Temporary Power Pole vs Generator: Break-Even Days

By DeskTech HQ · · 1 min read

Before the permanent electric service is back on, a rehab crew still needs power for tools and lights. A generator rents by the day. A temporary pole costs more to set up and then costs little. Which is cheaper depends on how long the job needs power.

The steps

  1. Get the setup cost of temporary power.
  2. Get the daily generator rental, including fuel.
  3. Break-even days = setup cost ÷ daily generator cost.
  4. Compare with the days your schedule needs power (debris and site costs before demolition).

A worked example

Example (illustrative arithmetic, not quotes)

Temporary power costs $1,100 to set up. A generator costs $55 a day with fuel. Every price is a made-up round number.

Days power is needed Generator total (days × $55) Generator − temporary power
10 $550 −$550 (generator cheaper)
20 $1,100 $0 (break-even)
30 $1,650 +$550 (temporary power cheaper)

Temporary power wins after twenty days: $1,100 ÷ $55. A short punch-list job favors the generator. A gut rehab that needs power for weeks favors the pole.

Include the nuisance cost. A generator needs refuelling, makes noise and can be stolen. Permits and inspection for the temporary service add time on the front end (budgeting for permits and inspections).

Making it routine

  1. Estimate the days power is needed.
  2. Get both prices in writing.
  3. Compute the break-even days.
  4. Keep generators outdoors and secured.

Run your own numbers

Use the free holding cost calculator below to see what schedule days cost on your own project.

Quick answers

How do I find the break-even?

Divide the setup cost of temporary power by the daily generator rental.

Why would a house need temporary power?

Tools need it before the permanent service is on, or when the service is being replaced.

Is a generator safe indoors?

No. Exhaust is a carbon monoxide risk. Keep it outside and follow the safety rules.

Who does the electrical work?

A licensed electrician, with permits where required.

Do the numbers in this guide apply to my project?

No. The prices are made up for the example. They are not quotes.

Keep reading

Flip project management

Daily Site Log: The Dispute Odds That Pay

Learn how to find the chance of a contractor dispute that makes ten minutes a day on a site log over a 60-day rehab worth the time it takes.

· 1 min read

This guide is general education, not legal, tax, or financial advice. Talk with a licensed professional about your situation.