Ask the Contractor to Sign the Draw Request Before Review
A draw request arrives with every figure filled in and no signature. You review it, approve it and later hear that the contractor never agreed to the numbers. Asking for a signature and date first takes two minutes. The question is how likely an unsigned request is to cause trouble for the step to pay.
The steps
- Price the step: minutes × the value of your time.
- Price an unsigned request: a repeated review or a dispute about who stood behind the figures.
- Break-even chance = step cost ÷ trouble cost.
- Review it properly (draw request review checklist).
A worked example
Example (illustrative arithmetic, not predictions)
The step takes 2 minutes at $60 an hour: $2. An unsigned request costs $100 to sort out. Every figure is a made-up round number.
| Chance an unsigned request causes trouble | Expected cost avoided (chance × $100) | Avoided − $2 |
|---|---|---|
| 1% | $1 | −$1 |
| 2% | $2 | $0 (break-even) |
| 6% | $6 | +$4 |
| 10% | $10 | +$8 |
The step pays at a 2% chance of trouble: $2 ÷ $100. Over many draws, it is easily exceeded.
Ask for a signature and date on every request before you review it, and send it back unreviewed if it is missing.
Making it routine
- Ask for a signature and date on every request.
- Check it before you review.
- Send it back if it is missing.
- Keep the signed request with the draw record.