Give the Contractor a Checklist of What to Attach to a Draw
The contractor sends a draw request with no lien waiver. The inspector is booked, the request waits and the crew gets paid late. A one-page checklist of what to attach takes eight minutes to write once. The question is how likely an incomplete request is for the checklist to pay.
The steps
- Price the checklist: minutes × the value of your time.
- Price an incomplete request: a week’s delay while the missing pieces are chased.
- Break-even chance = checklist cost ÷ delay cost.
- Review requests too (draw request review checklist).
A worked example
Example (illustrative arithmetic, not predictions)
The checklist takes 8 minutes at $60 an hour: $8. An incomplete request costs $200 in delay and chasing. Every figure is a made-up round number.
| Chance a request is incomplete | Expected cost avoided (chance × $200) | Avoided − $8 |
|---|---|---|
| 2% | $4 | −$4 |
| 4% | $8 | $0 (break-even) |
| 8% | $16 | +$8 |
| 12% | $24 | +$16 |
The checklist pays at a 4% chance of an incomplete request: $8 ÷ $200. Over many draws, it is plausible.
List what each draw needs as the loan documents say, give it to the contractor before the first draw and update it if the documents change.
Making it routine
- List what each draw needs as the documents say.
- Give it to the contractor before the first draw.
- Send it again with each draw reminder.
- Update it if the documents change.
Run your own numbers
Use the free fix-and-flip loan sizer below to see how a draw schedule works for a loan.