Borrower Scope Changes: How Lenders Approve Budget Moves
A rehab budget is a plan, and plans move. The lender’s job is not to freeze the plan but to make sure each move is understood, approved and written down before money follows it.
A routine for requests
- The borrower submits the request in writing, with the reason.
- The lender checks the effect on the total budget and the finished value.
- The lender compares it with the cap and the remaining holdback (budget review).
- The decision, and any conditions, are written down and signed.
- The revised budget replaces the old one for future draws (reviewing a draw request).
A worked example
Example (illustrative budget and cap, not a standard)
Take the $40,000 budget from the rehab estimates guide (rehab estimates). Assume a policy that allows moves of up to 10% of the budget, $4,000, without a fresh review. Every figure is a made-up round number.
| Line | Original | Request | Revised |
|---|---|---|---|
| Kitchen | $12,000 | +$3,000 | $15,000 |
| Bathrooms | $8,000 | $8,000 | |
| Flooring | $6,500 | $6,500 | |
| Paint | $4,500 | $4,500 | |
| Mechanical | $5,000 | $5,000 | |
| Exterior | $4,000 | −$3,000 | $1,000 |
| Total | $40,000 | $0 | $40,000 |
| Check | Calculation | Result |
|---|---|---|
| Amount moved | given | $3,000 |
| Share of the budget | $3,000 ÷ $40,000 | 7.5% |
| Against the 10% cap | $4,000 limit | within the cap |
| Exterior left | $4,000 − $3,000 | $1,000 |
The total does not change, and the move is within the cap, so the lender might approve it with conditions: a signed revised budget, and an inspection to confirm that the exterior work still needed for the sale, such as safety items, is covered by the $1,000.
Now suppose a second request moves $2,000 more.
| Check | Calculation | Result |
|---|---|---|
| Total moved | $3,000 + $2,000 | $5,000 |
| Share of the budget | $5,000 ÷ $40,000 | 12.5% |
| Against the 10% cap | over the cap |
The cumulative moves are over the cap, so this request goes back through a fresh review of the budget and the value.
Keep a record
- The request, the reason and the date.
- The decision and the conditions.
- The signed revised budget.
- A running total of moves against the cap (the complete loan file).